Reactor TrackerIndia

Kalpakkam PFBR

PFBR-500 · 470 MWe · Commissioning · commercial operation est. 2026

Current state

StatusCommissioning
DesignPFBR-500 (SFR)
Net capacity470 MWe
CountryIndia
VendorIGCAR/BHAVINI
Owner / operatorBHAVINI
Construction start2004-10
Original COD target—
Current COD estimate2026
Schedule slippage—

Notes

Status moved to commissioning 2026-09-28 (critical Apr 2026 + low-power physics + TG overhaul). 22-year build (FCD 2004). Rajya Sabha Jul 2026 (DAE): stepwise AERB clearances with quarterly inspections; next is power raise, grid sync, then commercial ops (date TBD). BHAVINI twin-unit fleet project in pre-project stage adjacent (context).

Milestone log

  • 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2026 (source)
  • 2026-04-06 — First criticality achieved (source)
  • 2026-06-27 — AEC chairman reviews low-power physics experiments + BHEL turbine-generator overhaul ahead of grid synchronisation (PIB; Hindu/Indian Express corroborate) (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.

Sources

  1. https://world-nuclear.org/information-library/current-and-future-generation/plans-for-new-reactors-worldwide
  2. https://pris.iaea.org/pris/
  3. https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=IN
  4. https://dae.gov.in/prototype-fast-breeder-reactor-at-kalpakkam-tamil-nadu-attains-first-criticality/
  5. https://www.pib.gov.in/PressReleasePage.aspx?PRID=2278389&lang=2&reg=48