Nuclear Plant Restarts Tracker

Bataan Nuclear Power Plant

Proposed · Philippines · Never-operated revival

Bataan is a 621 MWe Westinghouse PWR completed in 1984 but never fuelled or operated; President Corazon Aquino mothballed it in 1986. KHNP has been studying its rehabilitation for the Philippine Department of Energy since January 2025, but the host town of Morong declared itself a non-nuclear zone in June 2026 and the new regulator PhilATOM is not yet operating.

Background: Palisades fuel loading: Holtec restart timeline and what comes next · NRC reactor licensing process, explained

Current state

StatusProposed
CountryPhilippines
LocationNapot Point, Morong, Bataan
PlantBataan
Unit1
OperatorNational Power Corporation (Napocor), Philippine government
Reactor typePWR
Net capacity (MWe)621
Restart typeNever-operated revival
Shut down1986
Years offline40.3
RegulatorUnlicensed; any rehabilitation or operation needs approval of PhilATOM, created by RA 12305 (Sept 2025) but not yet operational
Local consentOpposed locally: Morong municipal council approved a non-nuclear-zone ordinance in June 2026
Cost estimateUSD 2.3bn

Notes

Never operated: years offline counts from the 1986 mothballing (year precision, mid-year assumed). cost estimate is DOE Undersecretary Sharon Garin's Nov 2022 figure of US$2.3bn to refurbish and start up (WNA); a 2008 IAEA mission estimated $800m-$1bn. Original construction cost $1.9bn (WNA). The Philippines targets first nuclear power by 2032, possibly via Bataan or SMRs.

Timeline

  • 1976-07 — Construction of the single 621 MWe Westinghouse unit began. (source)
  • 1984 — The plant was completed but was never loaded with fuel. (source)
  • 1986 — After the Chernobyl accident, President Corazon Aquino decided to mothball the plant. (source)
  • 2024-10-07 — The Philippine DOE and KHNP signed an MoU for a two-phase feasibility study on rehabilitating the plant, at KHNP's cost. (source)
  • 2025-01 — KHNP's feasibility study began, starting with a plant condition assessment. (source)
  • 2025-09 — President Marcos signed RA 12305 creating the independent regulator PhilATOM. (source)
  • 2026-06 — Morong's municipal council declared the municipality a non-nuclear zone. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Sources

  1. Nuclear Power in the Philippines — World Nuclear Association, checked 2026-10-11
  2. Korea to assess rehabilitation of Philippine plant — World Nuclear News, checked 2026-10-11
  3. Bataan nuclear plant's future hinges on new independent regulator — Asian Journal, checked 2026-10-11