LIS Technologies laser enrichment plant (Oak Ridge)

Planned · United States · Enrichment plant

Low-confidence record: sources are thin or conflict. Figures below are the best available public statements, not confirmed facts.

A proposed USD 1.38bn commercial laser enrichment plant by Laser Isotope Separation Technologies (LIST) on the former K-25 gaseous diffusion footprint in Oak Ridge, using its CRISLA infrared-laser process. LIST holds a Tennessee radioactive materials licence for UF6 testing and targets initial commercial operation before 2030, subject to NRC licensing and a final investment decision.

New to HALEU and enrichment? HALEU, explained: the fuel advanced reactors need · The U.S. nuclear fuel supply chain, explained

Current state

StatusPlanned
CountryUnited States
LocationFormer K-25 site, Oak Ridge, Tennessee
OperatorLaser Isotope Separation Technologies Inc. (LIST)
OwnershipPrivately held; founded 2023; ~USD 64m raised as of Jan 2026.
Facility typeEnrichment plant
TechnologyLaser
ProductsLEU
LicenseTennessee Radioactive Material Licence for UF6 testing (Dec 2025); NRC licensing process under way per company.
Government supportSelected Dec 2024 as one of six companies in DOE's LEU Enrichment Acquisition Program (no task order award in Jan 2026); support from Tennessee Nuclear Energy Fund.

Notes

No capacity, product enrichment level or firm schedule published; 'before 2030' is a company target. Feb 2026 release names the plant the LEU-3 Facility under 'Project F.U.E.L.' with Enveniam as lead integrator (search snippets only). No post-February 2026 progress found.

Timeline

  • 2024-12 — DOE selected LIST as one of six companies eligible for LEU enrichment acquisition task orders. (source)
  • 2025-12 — LIST received a Tennessee radioactive material licence allowing tests with UF6 feedstock. (source)
  • 2026-01 — LIST announced a USD 1.38bn commercial laser enrichment plant on the 206-acre former Duct Island parcel at the K-25 site. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related facilities

See all 29 facilities in the Uranium Enrichment & HALEU Tracker →

Sources

  1. LIST plans laser enrichment plant — Nuclear Engineering International, checked 2026-10-11
  2. Domestic Low Enriched Uranium Supply Chain — US Department of Energy (primary), checked 2026-10-11