Origin Nuclear and SGE signed an LOI to plan operations for a proposed 14-unit UK BWRX-300 fleet, adding an operator to a 4.2-GW project still in development.

A BWRX-300 reactor building at a UK project site, representing SGE and Origin Nuclear's proposed operations partnership. Illustration: NNN
A BWRX-300 reactor building at a UK project site, representing SGE and Origin Nuclear's proposed operations partnership. Illustration: NNN

Origin Nuclear, a subsidiary of Ontario Power Generation (OPG), and SGE SMR UK have signed a letter of intent to establish a joint venture to prepare for operating SGE's proposed UK fleet of 14 GE Vernova Hitachi BWRX-300 small modular reactors. The agreement adds a prospective operator to a project that SGE says would total 4.2 gigawatts across three sites; it does not authorize construction or create a binding build commitment.

Key facts

  • The letter of intent covers a proposed operating venture for 14 BWRX-300 units at three UK sites.
  • The fleet's proposed capacity is 4.2 GW, based on 300 megawatts electric per reactor.
  • SGE's UK proposal has progressed to a Preliminary Regulatory Assessment Deep Dive led by Great British Energy – Nuclear, according to the project partners.
  • SGE has said its first UK unit is planned to enter commercial operation in 2034; that remains a company target, not an approved schedule.

What happened

The proposed venture would give SGE SMR UK and Origin Nuclear a UK-based company focused on the operational side of the planned fleet. According to the companies' announcement as reported by World Nuclear News, Origin would support licensing, commissioning and operational readiness, then take responsibility for plant operations and centralized support services across the proposed sites.

Origin Nuclear is owned by OPG, the Canadian utility developing the first BWRX-300 at its Darlington New Nuclear Project. OPG's experience with the same reactor design is relevant to SGE's plan, but the UK projects will have their own licensing, construction and operating requirements. The LOI describes a future operating arrangement; it is not evidence that the UK project has secured permits, financing or final investment approval.

SGE, formerly Synthos Green Energy, has proposed a fleet of 14 reactors distributed across three locations. Its published plan calls for six units at the first site, with four at each of two later sites. The project company has not named all the sites in the available reporting. SGE's first unit target is commercial operation in 2034, a date that depends on multiple project decisions still ahead.

Why it matters

Naming an operator before a project reaches construction can help clarify how the developer intends to staff, license and manage a multi-unit fleet. Nuclear operations require a long-running organization for plant procedures, maintenance, training and regulatory compliance. Bringing in a company linked to the first BWRX-300 project could also give the UK proposal access to operating-model experience as that Canadian unit is developed.

The distinction between an operating plan and a construction commitment matters here. An LOI can establish intent and a workstream, but it does not mean that the joint venture is already formed, that the parties have agreed final commercial terms, or that the sites are authorized. It also does not settle who will fund construction or how electricity sales will support the proposed investment.

The fleet's size makes the operating question more than a staffing detail. SGE's proposed 14 units would use a standardized 300-MWe design, but the company must still translate a repeat-build ambition into site-specific licensing, construction sequencing and long-term operating arrangements. An operator's early participation may help shape those plans; it cannot remove the need for regulator review or project financing.

The wider BWRX-300 programme has moved beyond paper in Canada and the United States, though those projects have separate owners and regulatory tracks. The first unit is under construction at Darlington, while the Tennessee Valley Authority received an NRC construction permit for one planned unit at Clinch River. Those milestones show progress for the design, not approval of SGE's proposed UK sites.

Background

SGE's UK fleet proposal is part of a larger European development effort. In September, SGE, GE Vernova, Hitachi and Samsung C&T announced a memorandum of understanding to explore deployment opportunities and project development across Central and Eastern Europe and the UK. That cooperation concerns a regional BWRX-300 platform, while the new Origin arrangement focuses specifically on operating the proposed British fleet.

The UK project is also moving through a regulatory assessment process. GE Vernova's announcement said SGE's proposal had progressed to a Preliminary Regulatory Assessment Deep Dive led by Great British Energy – Nuclear. That step is not a construction license. The UK regulator's generic design assessment for the BWRX-300 and review of any specific project application are distinct from a developer's operating partnership.

NNN has covered Poland's separate proposal for 14 BWRX-300 reactors, as well as the NRC construction permit for the Clinch River BWRX-300. The new-builds and small modular reactors hub follows developments across designs and markets. Together, those stories underline why fleet plans need to be read at the right stage: a design milestone, a project proposal and an operating-company LOI each describe different pieces of a possible build.

What's next

The immediate next step is turning the letter of intent into an operating-company arrangement, with final terms and responsibilities still to be established. In parallel, SGE must advance its regulatory and project work for the proposed sites. The parties have not announced a binding construction decision or a financing package in the available report.

For the project to reach its stated first-unit target, SGE will need to show how site selection, regulatory assessment, financing, construction and operator readiness fit together. Origin's participation gives the proposal a named operational partner. The harder test will be whether the partnership and development process can produce an approved, financed project on a schedule that supports the 2034 target.

Background

The BWRX-300 is GE Vernova Hitachi's 300 MWe boiling-water small modular reactor, derived from the NRC-licensed ESBWR and fueled with GNF2 fuel already in commercial use. Unit 1 at Ontario Power Generation's Darlington site — the first Western SMR to reach construction — is being built with four units approved there totalling about 1,200 MW, and Poland's Orlen Synthos Green Energy is seeking state financing for 14 units across three sites. (As of August 2026.) Read the BWRX-300 explainer.

Questions

What did Origin Nuclear and SGE agree to?
They signed a letter of intent to establish a UK-based joint venture to support licensing, commissioning, operational readiness and operations for SGE's proposed BWRX-300 fleet.
How many reactors are proposed?
SGE's plan covers 14 BWRX-300 units across three UK sites, with a proposed total capacity of 4.2 GW.
Does the operating joint venture mean the reactors are approved?
No. The letter of intent concerns an operating model. The proposed projects still face regulatory, site, financing and construction decisions.

Sources

  1. OPG firm joins UK BWRX-300 project — World Nuclear News
  2. Polish company SGE hopes to deploy 14 BWRX-300 reactors in U.K. — American Nuclear Society
  3. SGE, GE Vernova, Hitachi and Samsung C&T sign MoU to advance BWRX-300 fleet deployment in Europe — GE Vernova

About Nuclear News Network

Nuclear News Network (NNN) is an independent publication covering the global nuclear energy sector — reactor construction, SMRs, fuel supply, policy, operations and fusion. NNN publishes a daily brief, same-day analysis of major developments, and reference guides used across the industry. Articles are produced by the NNN Newsroom, an editorial automation system with human oversight, under the publication's editorial standards. Ruben Seoane is the founder and main editor of NNN.