Mochovce 4 connects to Slovakia's grid for the first time
Slovakia's 471-MW Mochovce 4 synchronised with the grid on 15 October at 20% power, two days late, and now faces power-ascension tests and a 144-hour run.

Mochovce 4 starts power generation in Slovakia
Slovakia's 471-MW Mochovce 4 has started power generation, entering staged commissioning before grid synchronisation and a 144-hour full-power test.

Slovakia’s Mochovce 4 Reaches First Criticality After 39 Years
Slovakia’s 471-MWe Mochovce 4 has reached first criticality after 39 years of construction, moving the delayed unit into testing before grid connection.

Mochovce 4 preparing for physical start-up tests
Slovenské elektrárne says Mochovce unit 4 has finished assembly and sealing and is moving into the physical tests that precede first criticality.