Mochovce 4 connects to Slovakia's grid for the first time

Slovakia's 471-MW Mochovce 4 synchronised with the grid on 15 October at 20% power, two days late, and now faces power-ascension tests and a 144-hour run.

The Mochovce nuclear power plant in Slovakia with transmission lines in the foreground, as Mochovce 4 begins feeding electricity to the grid. Illustration: NNN
The Mochovce nuclear power plant in Slovakia with transmission lines in the foreground, as Mochovce 4 begins feeding electricity to the grid. Illustration: NNN

Slovakia's Mochovce 4 nuclear unit delivered electricity to the national grid for the first time on 15 October, when operator Slovenské elektrárne synchronised the first of its two turbine generators at 20:41 with the reactor at 20% power. The 471-MW unit is expected to cover about 13% of Slovak consumption, but full-power testing still lies ahead.

Key facts

What happened

Slovenské elektrárne said on 15 October that its Mochovce Unit 4 had begun supplying electricity to the Slovak power system for the first time. The first of the unit's two turbine generators was brought into phase with the grid at 20:41 local time, with the reactor operating at 20% of its power, the operator said.

"For the first time in history, Mochovce unit 4 is supplying electricity to the Slovak electricity system," Branislav Strýček, chairman and chief executive of Slovenské elektrárne, said, as reported by World Nuclear News. In the company's Slovak-language release, he called it a moment generations had waited for and a new low-emission source for the country.

The milestone arrived two days later than planned. On 13 October the company postponed the synchronisation and cancelled a press event after primary-voltage tests on the unit's generator produced an unusual response in voltage-measurement circuits. Those circuits sit in the non-nuclear part of the plant. The operator repeated part of the technical tests, said the event had no effect on nuclear safety, and described the step as standard practice during commissioning.

Why it matters

Grid synchronisation is the point at which a commissioning reactor stops being a test rig and becomes a generator on the national system. For Mochovce 4, it closes the gap between first criticality on 6 August and the start of power generation in late September, which NNN covered in Mochovce 4 starts power generation.

The scale matters for Slovakia. Slovenské elektrárne expects the unit to produce about 3.5 million MWh a year at full operation, about 13% of current national consumption. Nuclear already generated about 65% of Slovakia's electricity in 2025, citing IAEA data, from five units at Mochovce and Bohunice. A sixth unit would strengthen Slovakia's position among the most nuclear-reliant power systems in the world and reduce its need for imports.

It also matters for Europe's construction record. Mochovce 3 and 4 have been the region's longest-running completion project. A grid-connected Mochovce 4 shows that a long-stalled Soviet-era VVER-440 can be finished and brought to power under a modern EU regulatory regime, even if the schedule and cost have been far longer and higher than originally planned.

The 13 October delay is a reminder that commissioning is still under way. The fault was on the conventional side of the plant and was resolved within two days, but every step from here involves tests the regulator must accept before the unit moves on.

Background

Mochovce sits in western Slovakia and hosts the country's VVER-440/V-213 pressurised water reactors. Units 1 and 2 entered operation in 1998 and 1999. Construction of units 3 and 4 began in the 1980s and stalled in the early 1990s for lack of funding; completion work resumed in 2008. Mochovce 3 entered commercial operation in October 2023.

Unit 4 followed a long commissioning path in 2026. Fuel loading began in June, the reactor was sealed for physical start-up tests in July (NNN coverage), it reached criticality on 6 August and began generating power in September. NNN's Mochovce 4 tracker records each step with its source. Readers following new nuclear builds and SMRs can set the unit against other plants moving through commissioning.

Slovenské elektrárne produces about 66% of Slovakia's electricity and operates five nuclear units, 31 hydroelectric plants and two solar plants. The Slovak Republic holds a 34% stake in the company; the majority shareholder is Slovak Power Holding, owned by the Czech group Energetický a průmyslový holding.

What's next

The operator's next step is to synchronise the second turbine generator. After that, the unit will run prescribed tests at gradually increasing power until it reaches nominal output, under the supervision of the Nuclear Regulatory Authority of the Slovak Republic (ÚJD). The operator set out staged test points at 5%, 20%, 35%, 55%, 75% and 90% when power generation began (NNN coverage), and the final test will be a 144-hour run at 100% power.

Slovenské elektrárne has not announced a date for commercial operation. The milestones to watch are the second turbine's synchronisation, the first sustained operation at full power and the completion of the 144-hour run. Any further conventional-island issues like the one on 13 October would push those dates, but would not by themselves indicate a nuclear safety problem.

Questions

When was Mochovce 4 connected to the grid?
Slovenské elektrárne synchronised the first of the unit's two turbine generators with the Slovak grid at 20:41 local time on 15 October 2026, with the reactor operating at 20% of its power.
Is Mochovce 4 in commercial operation?
No. The second turbine generator still has to be synchronised, and the unit must pass tests at rising power levels and a 144-hour run at full power before commercial operation. No commercial operation date has been announced.
Why was the grid connection delayed?
On 13 October Slovenské elektrárne postponed synchronisation after an unusual response in voltage-measurement circuits in the non-nuclear part of the plant. It repeated part of the tests and said nuclear safety was not affected.
How much electricity will Mochovce 4 produce?
The operator expects about 3.5 million MWh a year at full operation, roughly 13% of Slovakia's current electricity consumption, from an installed capacity of 471 MW.

Sources

  1. Štvrtý blok Mochoviec Slovenských elektrární dodáva elektrinu do siete — Slovenské elektrárne
  2. Slovenské elektrárne odložili dnešné prifázovanie 4. bloku Mochoviec — Slovenské elektrárne
  3. Mochovce 4 connected to the grid — World Nuclear News
  4. Slovakia's Mochovce-4 Nuclear Power Plant Connected To Grid For First Time — NucNet

About Nuclear News Network

Nuclear News Network (NNN) is an independent publication covering the global nuclear energy sector — reactor construction, SMRs, fuel supply, policy, operations and fusion. NNN publishes a daily brief, same-day analysis of major developments, and reference guides used across the industry. Articles are produced by the NNN Newsroom, an editorial automation system with human oversight, under the publication's editorial standards. Ruben Seoane is the founder and main editor of NNN.