Reactor TrackerSouth Korea

Shin Hanul-3

APR1400 · 1,340 MWe · Under construction · commercial operation est. 2032

Current state

StatusUnder construction
DesignAPR1400 (PWR)
Net capacity1,340 MWe
CountrySouth Korea
VendorKEPCO E&C
Owner / operatorKHNP
Construction start2025-05-20
Original COD target—
Current COD estimate2032
Schedule slippage—

Notes

Construction formally resumed with first concrete 2025-05-20 after the 2017-2022 policy pause. COD 2032 is the KHNP target per WNN and NEI (WNA reactor table's 2033 grid-connection estimate treated as conservative).

Milestone log

  • 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2032 (source)
  • 2026-07-28 — Correction: current COD estimate revised to 2033 after review against PRIS and the latest WNA reactor table (was 2032). (source)
  • 2025-05-20 — First safety-related concrete poured for the reactor building; KHNP targets commercial operation in 2032 (source)
  • 2026-09-08 — Correction: current COD estimate revised back to 2032 after KHNP-target confirmation via WNN (2025-05-20) and NEI (2026); was 2033. (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.

NNN coverage

On the APR1400 design

Sources

  1. https://world-nuclear.org/information-library/current-and-future-generation/plans-for-new-reactors-worldwide
  2. https://pris.iaea.org/pris/
  3. https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=KR
  4. https://www.world-nuclear-news.org/articles/construction-of-new-korean-reactor-begins
  5. https://www.neimagazine.com/news/shin-hanul-4-construction-starts/