Armenian NPP Unit 2 (Metsamor 2)

Restarted · AM · Policy reversal

Metsamor 2 is a VVER-440 PWR at the Armenian Nuclear Power Plant, shut in March 1989 after the Spitak earthquake and restarted in November 1995 amid a severe energy crisis after 6.5 years offline. It remains Armenia's only operating reactor.

Background: Palisades fuel loading: Holtec restart timeline and what comes next · NRC reactor licensing process, explained

Current state

StatusRestarted
CountryAM
LocationMetsamor, Armavir Province
PlantArmenian NPP (Metsamor)
Unit2
OperatorArmenian Nuclear Power Plant CJSC
Reactor typePWR
Net capacity (MWe)416
Restart typePolicy reversal
Shut down1989-03-18
Restarted1995-10-26
Years offline6.6
RegulatorOperating (life extension work under way)

Notes

Historical precedent. Net capacity 416 MWe per WNA (2026, after upgrades); original 376 MWe net. Unit 1 remains shut and is being decommissioned. restarted is reactor restart (NucNet); grid connection followed in November 1995.

Timeline

  • 1989-03-18 — Unit 2 was shut down under a USSR Council of Ministers decision after the 1988 Spitak earthquake. (source)
  • 1993 — Armenia's government decided to restart unit 2 due to a severe energy crisis. (source)
  • 1995-10-26 — Unit 2 was restarted after a shutdown of more than six years. (source)
  • 1995-11 — Unit 2 was reconnected to the grid. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related units

See all 45 units in the Nuclear Plant Restarts Tracker →

Sources

  1. History — Armenian Nuclear Power Plant (primary), checked 2026-10-11
  2. Nuclear Power in Armenia — World Nuclear Association, checked 2026-10-11
  3. Armenian Power Reactor Restarts after 6-year Break — NucNet, checked 2026-10-11