Reactor TrackerUnited Kingdom

Hinkley Point C-1

EPR · 1,630 MWe · Under construction · commercial operation est. 2030

Current state

StatusUnder construction
DesignEPR (PWR)
Net capacity1,630 MWe
CountryUnited Kingdom
VendorEDF/Framatome
Owner / operatorNNB Generation Company (EDF)
Construction start2018-12-11
Original COD target2025
Current COD estimate2030
Schedule slippage+5 years

Britain's first new nuclear plant in a generation and the benchmark for Western large-reactor construction economics.

Notes

Flagship Western new-build and the canonical slippage story: 2030 start-up is five years past the original 2025 target. Unit 1 civils 94% by concrete volume at end-2025. Summer 2026: unit-1 fit-out accelerating per EDF video update; unit-2 vessel installed. ONR extended BYLOR improvement notices to Sep 14 2026 after a Jun formwork fall seriously injured a worker (INSite citing ONR) — regulatory watch item.

Milestone log

  • 2018-12-11 — First nuclear concrete poured (official construction start) (source)
  • 2024-01-23 — EDF announced revised schedule (Unit 1 2029-2031) and cost range £31-35bn (2015 money) (source)
  • 2026-01-20 — All 24 primary loop welds completed on Unit 1 (source)
  • 2026-03-02 — Unit 1 start-up pushed to 2030 on M&E productivity shortfall; cost estimate £35bn (2015 money) (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.

NNN coverage

At Hinkley Point C

On the EPR design

Sources

  1. https://pris.iaea.org/pris/
  2. https://www.edfenergy.com/energy/nuclear-new-build-projects/hinkley-point-c