Nuclear Fuel Services uranium purification and conversion services (U-Metal Project) for NNSA (Amendment 19): NRC fuel-cycle amendment review for Nuclear Fuel Services, Inc. — issued, 19.5 months from docketing to decision. Sourced dates and schedule.
Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands
Current state
| Type | Fuel-cycle amendment |
| Outcome | Issued |
| Applicant | Nuclear Fuel Services, Inc. |
| Facility | NFS site, Erwin, Tennessee |
| Docket | — |
| Submitted | 2021-11-18 |
| Docketed (accepted for review) | 2022-03-25 |
| NRC planned schedule | — |
| NRC target date | — |
| Final safety evaluation | — |
| Decision | 2023-11-07 |
| Review time (docketed → decision) | 19.5 mo |
| Submitted → decision | 23.6 mo |
| NRC-reported review duration | — |
| NRC-reported resources vs estimate | — |
Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.
Notes
Not enrichment/HALEU; included as a significant fuel-facility amendment with an EA and an ASLB proceeding. Hearing opportunity re-noticed Aug. 31, 2022; ASLB established Oct./Nov. 2022; per WISE (secondary, not verified in NRC docs) the Board denied ECAN’s petition on Jan. 30, 2023 (LBP-23-02). EA/FONSI Nov. 6, 2023. Docket number not captured. Licence/permit: SNM-124.
Timeline
- 2021-11-18 — Application received: “The NRC has received, by letter dated November 18, 2021, an application from Nuclear Fuel Services, Inc.” (source)
- 2022-03-25 — Accepted for review (docketed): “As documented in an administrative completeness review, dated March 25, 2022, NRC found the application, as supplemented, acceptable for a technical review.” (source)
- 2023-11-07 — Issued: “ML23255A178 - Amendment 19 – Approval Of Uranium Purification And Conversion Services (U-Metal Project) (Enterprise Project Identifier L-2021-LLA-0213) (4 page(s), 11/7/2023)” (source)
The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.
Also tracked
NNN coverage
About Nuclear Fuel Services site, Erwin
Related reviews
- Framatome Richland authorization of TRISO fuel fabrication in the Specialty Fuels Building and enrichment increase from 6.5 to up to 10.0 wt% U-235 (Amendment 21) Issued · 11.6 mo
- Framatome Richland site-wide enrichment limit increase from 5.0 to <6.5 wt% U-235 (Amendment 20) Issued · 10.7 mo
- American Centrifuge Plant Phase III HALEU operations for up to 9 years (to June 30, 2034) with possession limit increase (Amendment 29) Issued · 4.5 mo
- National Enrichment Facility amendment applying the <10 wt% LEU+ limit to recycling and support systems (LAR-24-01, Amendment 110) Issued · 8.1 mo
- American Centrifuge Plant continuation of HALEU operations to June 30, 2025 (Amendment 27) Issued · —
- National Enrichment Facility amendment raising enrichment limit from 5.5 to <10 wt% U-235 (LEU+) for production systems (LAR-23-02, Amendment 105) Issued · 9.4 mo
- Framatome Richland extension of criticality validation methodology and minimum margin of subcriticality to enrichments up to 20 wt% U-235 (Amendment 19) Issued · —
- American Centrifuge Plant increase in HALEU possession limits to produce ~1,400 kg HALEU UF6 (Amendment 24) Issued · —