NRC Licensing Review Tracker

Nuclear Fuel Services uranium purification and conversion services (U-Metal Project) for NNSA (Amendment 19)

Issued · Fuel-cycle amendment · Fuel cycle & storage

Nuclear Fuel Services uranium purification and conversion services (U-Metal Project) for NNSA (Amendment 19): NRC fuel-cycle amendment review for Nuclear Fuel Services, Inc. — issued, 19.5 months from docketing to decision. Sourced dates and schedule.

Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands

Current state

TypeFuel-cycle amendment
OutcomeIssued
ApplicantNuclear Fuel Services, Inc.
FacilityNFS site, Erwin, Tennessee
Docket—
Submitted2021-11-18
Docketed (accepted for review)2022-03-25
NRC planned schedule—
NRC target date—
Final safety evaluation—
Decision2023-11-07
Review time (docketed → decision)19.5 mo
Submitted → decision23.6 mo
NRC-reported review duration—
NRC-reported resources vs estimate—

Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.

Notes

Not enrichment/HALEU; included as a significant fuel-facility amendment with an EA and an ASLB proceeding. Hearing opportunity re-noticed Aug. 31, 2022; ASLB established Oct./Nov. 2022; per WISE (secondary, not verified in NRC docs) the Board denied ECAN’s petition on Jan. 30, 2023 (LBP-23-02). EA/FONSI Nov. 6, 2023. Docket number not captured. Licence/permit: SNM-124.

Timeline

  • 2021-11-18 — Application received: “The NRC has received, by letter dated November 18, 2021, an application from Nuclear Fuel Services, Inc.” (source)
  • 2022-03-25 — Accepted for review (docketed): “As documented in an administrative completeness review, dated March 25, 2022, NRC found the application, as supplemented, acceptable for a technical review.” (source)
  • 2023-11-07 — Issued: “ML23255A178 - Amendment 19 – Approval Of Uranium Purification And Conversion Services (U-Metal Project) (Enterprise Project Identifier L-2021-LLA-0213) (4 page(s), 11/7/2023)” (source)

The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.

Also tracked

NNN coverage

About Nuclear Fuel Services site, Erwin

Related reviews

See all 75 reviews in the NRC Licensing Review Tracker →

Sources

  1. https://www.nrc.gov/docs/ML2325/ML23255A177.pdf
  2. https://www.federalregister.gov/documents/2022/08/31/2022-18775/nuclear-fuel-services-inc
  3. https://www.federalregister.gov/documents/2023/11/06/2023-24408/nuclear-fuel-services-inc-u-metal-project
  4. https://www.wise-uranium.org/eopnfs.html