American Centrifuge Plant increase in HALEU possession limits to produce ~1,400 kg HALEU UF6 (Amendment 24)

Issued · Fuel-cycle amendment · Fuel cycle & storage

American Centrifuge Plant increase in HALEU possession limits to produce ~1,400 kg HALEU UF6 (Amendment 24): NRC fuel-cycle amendment review for American Centrifuge Operating, LLC (Centrus Energy Corp.) — issued. Sourced dates and schedule.

Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands

Current state

TypeFuel-cycle amendment
OutcomeIssued
ApplicantAmerican Centrifuge Operating, LLC (Centrus Energy Corp.)
FacilityAmerican Centrifuge Plant, Piketon, Ohio
Docket70-7004
Submitted2023-02-13
Docketed (accepted for review)—
NRC planned schedule—
NRC target date—
Final safety evaluation—
Decision2024-09-20
Review time (docketed → decision)—
Submitted → decision19.2 mo
NRC-reported review duration—
NRC-reported resources vs estimate—

Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.

Notes

NRC page says the Feb. 2023 application sought 1,400 kg "by December 31, 2023", but approval came Sept. 20, 2024 after supplements through Mar. 7, 2024. Acceptance date not found. Submitted pre-ADVANCE, decided post. Licence/permit: SNM-2011.

Timeline

  • 2023-02-13 — Application received: “The proposed action is in accordance with the licensee's application dated February 13, 2023, as supplemented by letters dated June 29, 2023, February 15, 2024, and March 7, 2024.” (source)
  • 2024-09-20 — Issued: “On September 20, 2024, the NRC issued Amendments 24 to ACO to increase ACO’s possession limits” (source)

The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.

Also tracked

NNN coverage

About American Centrifuge Plant (Piketon)

Related reviews

See all 75 reviews in the NRC Licensing Review Tracker →

Sources

  1. https://www.nrc.gov/facilities-safety/fuel-cycle-facilities/new-fuel-cycle-facility-licensing/gas-centrifuge-enrichment-facility-licensing/centrus-energy-corpamerican-centrifuge-operating-llc-formerly-usec-inc-gas-centrifuge-enrichme
  2. https://www.federalregister.gov/documents/2024/09/19/2024-21276/american-centrifuge-operating-llc-american-centrifuge-plant-environmental-assessment-and-finding-of