Nuclear Decommissioning Tracker

Millstone Unit 1

SAFSTOR · United States · Deferred (SAFSTOR)

Millstone 1, a 652 MWe GE BWR shut down in 1995, is in SAFSTOR on the site of Dominion's operating Millstone Units 2 and 3. The owner plans to keep it in safe storage until 2048, and the NRC estimates closure in 2056.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusSAFSTOR
CountryUnited States
LocationWaterford, Connecticut
SiteMillstone Power Station
UnitsUnit 1
Unit count1
Reactor typesBWR
Net capacity (MWe)652
Owner / licenseeDominion Nuclear Connecticut
StrategyDeferred (SAFSTOR)
Final shutdown1995-11-04
Target completion2056
Spent fuelFuel moved to the spent fuel pool in November 1995; site holds a general-license ISFSI.

Notes

SAFSTOR until 2048 per NRC page.

Timeline

  • 1970-12-28 — Millstone 1 entered commercial operation. (source)
  • 1995-11-04 — Unit 1 was shut down. (source)
  • 1998-07-21 — The licensee certified permanent cessation of operations to the NRC. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Millstone - Unit 1 — U.S. NRC (primary), checked 2026-10-11
  2. Locations of Power Reactor Sites Undergoing Decommissioning — U.S. NRC (primary), checked 2026-10-11