Peach Bottom Unit 1

SAFSTOR · United States · Deferred (SAFSTOR)

Peach Bottom 1 was a 200 MWt high-temperature gas-cooled prototype that ran from 1967 to 1974. It has been in SAFSTOR since 1978 with fuel removed to Idaho, and final decommissioning is deferred until operating Units 2 and 3 shut; the NRC estimates closure in 2074.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusSAFSTOR
CountryUnited States
LocationDelta, Pennsylvania
SitePeach Bottom Atomic Power Station
UnitsUnit 1
Unit count1
Reactor typesHTGR
Owner / licenseeConstellation Energy Generation
StrategyDeferred (SAFSTOR)
Final shutdown1974-10-31
Target completion2074
Spent fuelAll spent fuel shipped to a DOE facility in Idaho; pool drained and decontaminated.
Notable issueNRC exemption allows completion beyond 60 years of shutdown.

Timeline

  • 1967-06 — Peach Bottom 1 began operating. (source)
  • 1974-10-31 — The reactor shut down for the final time. (source)
  • 1978-02 — Decommissioning activities placing it in SAFSTOR were completed. (source)
  • 2023 — The licensee requested an alternative schedule to finish decommissioning beyond 60 years. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Peach Bottom - Unit 1 — U.S. NRC (primary), checked 2026-10-11
  2. Locations of Power Reactor Sites Undergoing Decommissioning — U.S. NRC (primary), checked 2026-10-11