Nuclear Decommissioning Tracker

Sellafield (incl. Calder Hall)

Active dismantling · United Kingdom · Mixed

Sellafield is Britain's largest and most hazardous nuclear clean-up, covering the Calder Hall Magnox reactors (the world's first industrial-scale grid-connected nuclear station, 1956-2003) alongside legacy reprocessing plants, ponds and silos. The NDA expects clean-up to run until 2125 at an undiscounted cost of £136bn; Calder Hall was defueled in 2019 and its reactors are in care and maintenance.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusActive dismantling
CountryUnited Kingdom
LocationSeascale, Cumbria, England
SiteSellafield
UnitsCalder Hall 1, Calder Hall 2, Calder Hall 3, Calder Hall 4
Unit count4
Reactor typesMagnox
Net capacity (MWe)200
Owner / licenseeNuclear Decommissioning Authority (site licensee: Sellafield Ltd)
Decommissioning contractorSellafield Ltd
StrategyMixed
Final shutdown2003-03-31
Decommissioning start2003
Target completion2125
Cost estimateGBP 136bn (as of 2025-06-04)
Spent fuelCalder Hall defueled by September 2019 (38,953 fuel rods sent for Magnox reprocessing); site stores much of the UK's spent fuel and plutonium.
Notable issuePublic Accounts Committee criticises repeated cost overruns and delays on major Sellafield projects; cost estimate up 18.8% since 2019.

Notes

Scope is the whole Sellafield site clean-up (reactors are a small part). Cost is undiscounted and covers all Sellafield decommissioning, not just Calder Hall. Calder Hall 4 x 50 MWe net per WNN. PAC report published 4 June 2025.

Timeline

  • 1956-10-17 — Calder Hall was opened as the world's first industrial-scale nuclear power station connected to a national grid. (source)
  • 2003-03-31 — Calder Hall closed after 47 years of operation. (source)
  • 2007-09 — Calder Hall's four cooling towers were demolished. (source)
  • 2011 — Defueling of Calder Hall's reactors began. (source)
  • 2019-09-03 — Sellafield Ltd completed defueling of Calder Hall; the reactor buildings entered care and maintenance. (source)
  • 2025-06-04 — Parliament's Public Accounts Committee reported the Sellafield clean-up would cost £136bn and last until 2125. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Decommissioning Sellafield (Public Accounts Committee report) — UK House of Commons Public Accounts Committee (primary), checked 2026-10-11
  2. Decommissioning the world's first commercial nuclear power station — Nuclear Decommissioning Authority (primary), checked 2026-10-11
  3. Sellafield completes defueling of Calder Hall — World Nuclear News, checked 2026-10-11
  4. Nuclear Power in the United Kingdom — World Nuclear Association, checked 2026-10-11