Brennilis (Monts d'Arrée EL-4)

Active dismantling · France · Mixed

Brennilis was a 70 MWe heavy-water, gas-cooled prototype that ran from 1967 to 1985 and has become a byword for slow French decommissioning. After a 2007 court annulment and partial work, a full dismantling decree was issued in September 2023; EDF began the final phase in December 2024 and targets a bare site by 2041.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusActive dismantling
CountryFrance
LocationBrennilis, Finistère
SiteBrennilis
UnitsEL-4
Unit count1
Reactor typesHWGCR
Owner / licenseeEDF
StrategyMixed
Final shutdown1985-07-31
Decommissioning start1985
Target completion2041
Spent fuelAll irradiated fuel removed by 1992.
Notable issueAsbestos and mercury discoveries delayed handling-crane upgrades, but reactor fuel-channel removal is still planned to start in 2027.

Notes

70 MWe capacity is commonly cited but not in the sources reviewed (capacity left not recorded). A press report puts full dismantling cost at about €850m (not recorded: date unclear).

Timeline

  • 1966-12-23 — The reactor first went critical. (source)
  • 1985-07-31 — Power production permanently ended. (source)
  • 2007-06-06 — France's Conseil d'État annulled the 2006 decree authorising full dismantling. (source)
  • 2011-07-27 — A decree authorised partial dismantling excluding the reactor block. (source)
  • 2023-09-26 — Decree 2023-898 prescribed complete dismantling of the installation. (source)
  • 2024-12 — The plant entered its final dismantling phase. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

NNN coverage

About EDF

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Monts d'Arrée EL4-D (Centrale nucléaire de Brennilis) — ASNR (primary), checked 2026-10-11
  2. La centrale nucléaire de Brennilis — EDF (primary), checked 2026-10-11
  3. Centrale nucléaire de Brennilis : dernière étape de la déconstruction — Andra (primary), checked 2026-10-11