Nuclear Decommissioning Tracker

Dounreay (DFR and PFR fast reactors)

Active dismantling · United Kingdom · Immediate dismantling

Low-confidence record: sources are thin or conflict. Figures below are the best available public statements, not confirmed facts.

Dounreay was the UK's fast-reactor research centre from 1955 to 1994, including the Dounreay Fast Reactor and the 250 MWe Prototype Fast Reactor, and is now Scotland's largest nuclear clean-up. All reactor fuel has been removed, but residual sodium coolant and a large fuel cycle area remain; the interim end-state date has slipped into the 2070s.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusActive dismantling
CountryUnited Kingdom
LocationThurso, Caithness, Scotland
SiteDounreay
UnitsDounreay Fast Reactor (DFR), Prototype Fast Reactor (PFR)
Unit count2
Reactor typesFBR (sodium/NaK-cooled)
Owner / licenseeNuclear Decommissioning Authority (site licensee: Nuclear Restoration Services – Dounreay)
Decommissioning contractorNuclear Restoration Services
StrategyImmediate dismantling
Final shutdown1994
Cost estimateGBP 7.9bn (as of 2024-04)
Spent fuelAll fuel and breeder material removed from PFR; last DFR breeder material being moved to Sellafield.
Notable issueInterim end state slipped from a 2023 target to around 2078, with total spend rising to almost £8bn.

Notes

Research/prototype site rather than a commercial plant; included for search demand. Cost figure is press-reported (worker briefing), not an official NDA publication; target year ~2078 not confirmed by NDA so target completion not recorded. PFR 250 MWe is commonly cited but not in the sources reviewed.

Timeline

  • 1955 — Dounreay became the UK's centre of fast reactor research and development. (source)
  • 1994 — Fast reactor research ended at Dounreay with PFR's shutdown. (source)
  • 2012-05 — A specific interim end-state date of 14 September 2023 was proposed. (source)
  • 2024-04 — Reports said spending would run to around 2078 at a total cost of about £7.9bn. (source)
  • 2025-03-29 — Dounreay employed about 1,400 people with annual spend of about £225m as clean-up continued. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Dounreay — Office for Nuclear Regulation (primary), checked 2026-10-11
  2. Dounreay at forefront of nuclear decommissioning 70 years — Northern Times, checked 2026-10-11
  3. New end date at Dounreay will mean a spend of £7.9bn — Northern Times, checked 2026-10-11
  4. About NRS — NRS Site Stakeholder Groups (primary), checked 2026-10-11