Kashiwazaki-Kariwa Unit 7

Approved · Japan · Post-Fukushima restart

Kashiwazaki-Kariwa 7 is a 1,315 MWe (net) TEPCO ABWR with NRA approval (2017) and Niigata local consent (2025), but it cannot restart until its specialised anti-terrorism facility is finished, scheduled for August 2029. TEPCO removed its fuel in October 2025 and prioritised unit 6.

Background: Palisades fuel loading: Holtec restart timeline and what comes next · NRC reactor licensing process, explained

Current state

StatusApproved
CountryJapan
LocationKashiwazaki and Kariwa, Niigata Prefecture
PlantKashiwazaki-Kariwa
Unit7
OperatorTokyo Electric Power Company (TEPCO)
Reactor typeBWR
Net capacity (MWe)1,315
Restart typePost-Fukushima restart
Shut down2011-08-23
Restart target2029
Years offline15.1
RegulatorNRA approval 2017-12-27; restart blocked until specialised safety facility completion (scheduled Aug 2029)
Local consentNiigata governor consented 2025-11-21; prefectural assembly backed the decision 2025-12-22

Notes

restart target '2029' reflects EIA ('delayed until 2029-2030') and WNA (cannot restart before SSF completion, Aug 2029). years offline measured to 2026-10-11.

Timeline

  • 2011-08-23 — Kashiwazaki-Kariwa 7 went offline for a periodic inspection. (source)
  • 2017-12-27 — The NRA approved units 6 and 7. (source)
  • 2024-04-26 — TEPCO completed fuel loading. (source)
  • 2025-10-21 — TEPCO began removing fuel from the reactor. (source)
  • 2025-11-21 — The Niigata governor consented to restarting units 6 and 7. (source)
  • 2025-12-22 — The prefectural assembly backed the governor. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related units

See all 45 units in the Nuclear Plant Restarts Tracker →

Sources

  1. Current Status of Nuclear Power Plants in Japan as of August 7, 2026 — Japan Atomic Industrial Forum (JAIF) (primary), checked 2026-10-11
  2. Nuclear Power in Japan — World Nuclear Association, checked 2026-10-11
  3. Niigata governor consents to restart of Kashiwazaki-Kariwa reactors — World Nuclear News, checked 2026-10-11
  4. Restart of Kashiwazaki-Kariwa reactors approved by regional assembly — World Nuclear News, checked 2026-10-11
  5. Nuclear reactor restart in Japan will likely displace natural gas electricity generation — U.S. Energy Information Administration (primary), checked 2026-10-11