Orano Georges Besse II enrichment plant (Tricastin)

Expanding · France · Enrichment plant

Orano's centrifuge enrichment plant at Tricastin, rated at 7.5 million SWU a year across 14 modules. A roughly EUR 1.7bn extension adding four identical modules and 2.5 million SWU broke ground in October 2024, had over 70% of its concrete poured by November 2025 and was authorized by government decree in April 2026; first production is planned for 2028 and full commissioning for 2030.

New to HALEU and enrichment? HALEU, explained: the fuel advanced reactors need · The U.S. nuclear fuel supply chain, explained

Current state

StatusExpanding
CountryFrance
LocationTricastin site, Drome/Vaucluse
OperatorOrano
OwnershipOrano is majority owned by the French state.
Facility typeEnrichment plant
TechnologyGas centrifuge
ProductsLEU
Capacity (tSWU/yr)7,500
Target capacity (tSWU/yr)10,000
Target year2030
LicenseBuilding permit granted June 2024; government decree authorizing the capacity increase published 30 Apr 2026; first UF6 introduction into the extension requires prior approval of the French nuclear safety regulator (ASNR).
Government supportEuropean Investment Bank financing of EUR 400m for the extension (reported by NEI Magazine).

Notes

Cost ~EUR 1.7bn. New modules to come online progressively from 2028, full commissioning 2030. Orano also says it is prepared to supply enrichment above 6% by 2030 given firm customer commitments (Orano HALEU page, search snippet).

Timeline

  • 2023-10 — Orano's board approved an investment of nearly EUR 1.7bn to extend Georges Besse II by four modules. (source)
  • 2024-06 — The building permit for the extension was granted. (source)
  • 2024-10 — Orano held the groundbreaking ceremony for the extension after work began in late summer 2024. (source)
  • 2025-03-10 — The European Investment Bank granted a EUR 400m loan for the extension. (source)
  • 2025-11-20 — Orano hosted an EIB delegation at Tricastin, reporting over 70% of the extension's concrete poured and the project on schedule and within budget. (source)
  • 2026-04-30 — The French government published the decree authorizing the increase of Georges Besse II capacity from 7.5 to 10 million SWU. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

NNN coverage

About Orano

Related facilities

See all 29 facilities in the Uranium Enrichment & HALEU Tracker →

Sources

  1. Annual Activity Report 2025 - Georges Besse II extension — Orano (primary), checked 2026-10-11
  2. Progress on Georges Besse 2 plant extension project — Orano (primary), checked 2026-10-11
  3. Georges Besse II: extension decree marks halfway point in the project — SFEN, checked 2026-10-11
  4. EIB reviews Orano's enrichment expansion — Nuclear Engineering International, checked 2026-10-11
  5. Uranium Enrichment (updated 29 Sep 2026) — World Nuclear Association, checked 2026-10-11
  6. Plans to expand the enrichment capacity — International Panel on Fissile Materials, checked 2026-10-11