Reactor TrackerSlovakia

Mochovce-4

VVER-440/V-213 · 440 MWe · Commissioning · commercial operation est. 2026

Current state

StatusCommissioning
DesignVVER-440/V-213 (PWR)
Net capacity440 MWe
CountrySlovakia
VendorŠkoda/Rosatom lineage
Owner / operatorSlovenské elektrárne
Construction start1987
Original COD target—
Current COD estimate2026
Schedule slippage—

Notes

Soviet-era start; completion resumed decades later - unit 3 entered service 2023. First criticality (2026-08-05/06) now confirmed by operator press release, ANS Nuclear Newswire and trade press. Power generation from 2026-09-21; grid synchronisation at 20% and 144-hour demonstration run still ahead, so commercial operation likely late 2026 to Q1 2027.

Milestone log

  • 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2026 (source)
  • 2026-06-29 — First fuel assembly loaded into the reactor at 15:45 local time, beginning fuel load (operator announcement via WNN, 2026-06-30) (source)
  • 2026-07-20 — Reactor assembly and sealing completed; unit entered physical start-up tests preceding first criticality (Slovenske elektrarne via WNN) (source)
  • 2026-08-05 — First criticality reported (NucNet, published 2026-08-07 with 2026-08-05 dateline); single trade-press source so far - awaiting Slovenske elektrarne / IAEA PRIS confirmation (source)
  • 2026-08-06 — First criticality confirmed by operator Slovenske Elektrarne (press release 2026-08-07): reactor critical at 22:10, minimum controlled power at 22:31; power ascension tests to follow (source)
  • 2026-09-21 — Power generation begins at 15:33 (operator via WNN); staged commissioning at 5/20/35/55/75/90% with grid synchronisation at 20%, then 144-hour full-power run before commercial operation (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.

NNN coverage

About Mochovce-4

On the VVER-440 design

Sources

  1. https://world-nuclear.org/information-library/current-and-future-generation/plans-for-new-reactors-worldwide
  2. https://www.world-nuclear-news.org/articles/fuel-loading-begins-at-slovakias-mochovce-4
  3. https://www.world-nuclear-news.org/articles/mochovce-4-reactor-assembly-completed
  4. https://www.nucnet.org/news/slovakia-s-mochovce-4-nuclear-power-plant-reaches-first-criticality-8-5-2026
  5. https://www.seas.sk/pre-media/tlacove-spravy/slovenske-elektrarne-ozivili-reaktor-4-bloku-jadrovej-elektrarne-mochovce/
  6. https://www.ans.org/news/article-8287/slovakias-newest-reactor-achieves-criticality/
  7. https://pris.iaea.org/pris/
  8. https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=SK
  9. https://www.world-nuclear-news.org/articles/power-start-up-for-mochovce-4