Sizewell C-1

EPR · 1,630 MWe · Under construction · commercial operation est. 2035

Current state

StatusUnder construction
DesignEPR (PWR)
Net capacity1,630 MWe
CountryUnited Kingdom
VendorEDF/Framatome
Owner / operatorSizewell C Ltd (UK Govt/EDF/investors)
Construction start2025
Original COD target2035
Current COD estimate2035
Schedule slippage0 years

Notes

Replicate-and-learn thesis vs Hinkley. £38bn (2024 prices); commercial operation guided mid-to-late 2030s — 2035 estimate is the optimistic end. Aug 2026 road-contractor change flagged as a schedule risk by local press; Sizewell C denies delay.

Milestone log

  • 2025-07-22 — UK final investment decision; ~£38bn project cost announced (source)
  • 2025-11-15 — Financial close reached with private investors (source)
  • 2026-02-01 — ~2,000 workers on site as construction ramps (source)
  • 2026-08-26 — Sizewell C ends commercial talks with Galliford Try for the Link Road and Two Village Bypass; project says no schedule impact, but local press flags delay risk to the £38bn build (source)
  • 2026-09-09 — First commercial freight train arrives via the Green Rail Route (1,000+ t aggregates); ~100 kt by rail before Christmas, up to 4 trains/day at peak (Sizewell C + BBC + NCE) (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.

NNN coverage

At Sizewell C

On the EPR design

Sources

  1. https://www.sizewellc.com/
  2. https://www.the-independent.com/news/uk/home-news/sizewell-c-nuclear-project-roads-delay-b3039712.html
  3. https://www.sizewellc.com/news-views/sizewell-c-hits-major-milestone-as-first-commercial-freight-train-arrives-on-site/