Eden Isotope Production Complex construction permit (non-power reactor and production facility): NRC construction permit review for Eden Radioisotopes, LLC — under review. Sourced dates and schedule.
Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands
Current state
| Type | Construction permit |
| Outcome | Under review |
| Applicant | Eden Radioisotopes, LLC |
| Facility | Eden Isotope Production Complex (Lea County, New Mexico) |
| Docket | 50-619 |
| Submitted | 2026-05-05 |
| Docketed (accepted for review) | 2026-06-15 |
| NRC planned schedule | — |
| NRC target date | — |
| Final safety evaluation | — |
| Decision | — |
| Review time (docketed → decision) | — |
| Submitted → decision | — |
| NRC-reported review duration | — |
| NRC-reported resources vs estimate | — |
Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.
Notes
NRC target for the final safety evaluation: 2027-10. Medical-isotope non-power production/utilization facility, listed by NRC under advanced reactor application projects. Docket 50-619 from the ASLB notice (FR 2026-19294, 'Docket No. 50-619-CP'); pre-application project 99902077. Submitted: NRC page header: 'May 5, 2026 (date of application submittal)'; its milestone table reads 'Application Tendered | 5/5/2025 - A' (year typo). Final safety evaluation: Target October 2027. Decision: Under review.
Timeline
- 2026-05-05 — Application received: “The construction permit application is dated May 5, 2026.” (source)
- 2026-06-15 — Accepted for review (docketed): “The application was docketed on June 15, 2026.” (source)
The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.
Related reviews
- University of Illinois KRONOS MMR research reactor construction permit Under review · —
- Atomic Alchemy Versatile Isotope Production Reactor (VIPR) construction permit (Part 1) Withdrawn · —
- Clinch River Nuclear Unit 1 (BWRX-300) construction permit Issued · 14.7 mo
- Long Mott Generating Station (four Xe-100 modules) construction permit Under review · —
- Kemmerer Power Station Unit 1 (Natrium) construction permit Issued · 21.6 mo
- Kairos Hermes 2 two-unit test reactor facility construction permits Issued · 14.4 mo
- Abilene Christian University Molten Salt Research Reactor construction permit Issued · 21.9 mo
- Kairos Hermes test reactor construction permit Issued · 24.5 mo
See all 75 reviews in the NRC Licensing Review Tracker →