NRC Licensing Review Tracker

Kairos Hermes 2 two-unit test reactor facility construction permits

Issued · Construction permit · New reactors

Kairos Hermes 2 two-unit test reactor facility construction permits: NRC construction permit review for Kairos Power LLC — issued, 14.4 months from docketing to decision. Sourced dates and schedule.

Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands

Current state

TypeConstruction permit
OutcomeIssued
ApplicantKairos Power LLC
FacilityHermes 2 test reactor facility (Oak Ridge, Tennessee)
Docket50-611, 50-612
Submitted2023-07-14
Docketed (accepted for review)2023-09-11
NRC planned schedule14 months
NRC target date—
Final safety evaluation2024-07-19
Decision2024-11-21
Review time (docketed → decision)14.4 mo
Submitted → decision16.3 mo
NRC-reported review duration10 months
NRC-reported resources vs estimate43% under

Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.

Notes

The efficiency table marks Hermes 2 with an asterisk; the footnote text was not present in the fetched page. The same page credits 'proactive exemptions to leverage environmental information from the Kairos Hermes 1 review' (environmental assessment instead of EIS). FSE (07/19/2024) came 10 days after the ADVANCE Act was signed; most of the review predates the Act. Docketed: NRC page: schedule letter issued 10/11/2023.

Timeline

  • 2023-07-14 — Application received: “The application for the construction permits was received on July 14, 2023.” (source)
  • 2023-09-11 — Accepted for review (docketed): “This action becomes effective on September 11, 2023.” (source)
  • 2024-07-19 — Final safety evaluation issued. (source)
  • 2024-11-20 — Commission mandatory hearing. (source)
  • 2024-11-21 — Issued: “The Construction Permits CPTR-7 and CPTR-8 were issued on November 21, 2024.” (source)

The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.

Also tracked

NNN coverage

About Kairos Power

Related reviews

See all 75 reviews in the NRC Licensing Review Tracker →

Sources

  1. https://www.nrc.gov/licensing-applications/non-power-facilities/new-facility-licensing/hermes-2-kairos-application
  2. https://www.federalregister.gov/d/2023-16605
  3. https://www.federalregister.gov/d/2023-19935
  4. https://www.federalregister.gov/d/2024-20812
  5. https://www.federalregister.gov/d/2024-28025
  6. https://www.nrc.gov/regulations-legislation/effectiveness-efficiency-and-timeliness-initiatives-that-support-unleashing-american-energy/licensing-efficiencies