Kairos Hermes test reactor construction permit: NRC construction permit review for Kairos Power LLC — issued, 24.5 months from docketing to decision. Sourced dates and schedule.
Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands
Current state
| Type | Construction permit |
| Outcome | Issued |
| Applicant | Kairos Power LLC |
| Facility | Hermes test reactor (Oak Ridge, Tennessee) |
| Docket | 50-7513 |
| Submitted | 2021-09-29 |
| Docketed (accepted for review) | 2021-11-29 |
| NRC planned schedule | 21 months |
| NRC target date | — |
| Final safety evaluation | 2023-06-13 |
| Decision | 2023-12-14 |
| Review time (docketed → decision) | 24.5 mo |
| Submitted → decision | 26.5 mo |
| NRC-reported review duration | 18 months |
| NRC-reported resources vs estimate | 6% under |
Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.
Notes
Non-power test reactor licensed under 10 CFR 50 (section 104c). FEIS finalized 08/17/2023. NRC's executed months (18) appear to measure the safety review (docketing 11/2021 to FSE 06/2023 is ~18.5 months), not to permit issuance. Submitted: Phased: PSAR submitted 9/29/2021; Environmental Report submitted 10/31/2021. NRC milestone table lists 'Application Tendered 10/31/2021 - A*' with footnote '*Safety Preliminary Safety Evaluation Report (PSAR) submitted 9/29/2021. Environmental Report Submitted 10/31/21' (https://www.nrc.gov/licensing-applications/non-power-facilities/new-facility-licensing/hermes-kairos-application). Docketed: NRC page: 'Docketing Decision Letter Issued/Acceptance Review Complete 11/29/2021 - A'; schedule letter issued 12/15/2021. Decision: NRC project page milestone table lists '_Construction Permit Decision_ 12/12/2023 - A'; project overview and FR both say issued December 14, 2023.
Timeline
- 2021-09-29 — Application received: “The application for the construction permit was received on September 29, 2021.” (source)
- 2021-11-29 — Accepted for review (docketed): “This action becomes effective on November 29, 2021.” (source)
- 2023-06-13 — Final safety evaluation issued. (source)
- 2023-10-19 — Commission mandatory hearing. (source)
- 2023-12-14 — Issued: “The Construction Permit No. CPTR-6 was issued on December 14, 2023.” (source)
The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.
Also tracked
NNN coverage
About Kairos Power
- Nature Outlook puts SMRs at center of AI power debate 2026-08-30
- Nuclear power for data centers, explained: every deal tracked 2026-10-01
- HALEU, explained: the fuel advanced reactors need 2026-08-27
- DOE nuclear funding, explained: every program paying for the buildout 2026-08-05
- Top SMR developers in 2026, ranked by what they've actually built 2026-08-05
- Small modular reactors, explained: who is building them worldwide 2026-07-09
Related reviews
- Kairos Hermes 2 two-unit test reactor facility construction permits Issued · 14.4 mo
- Eden Isotope Production Complex construction permit (non-power reactor and production facility) Under review · —
- University of Illinois KRONOS MMR research reactor construction permit Under review · —
- Atomic Alchemy Versatile Isotope Production Reactor (VIPR) construction permit (Part 1) Withdrawn · —
- Clinch River Nuclear Unit 1 (BWRX-300) construction permit Issued · 14.7 mo
- Long Mott Generating Station (four Xe-100 modules) construction permit Under review · —
- Kemmerer Power Station Unit 1 (Natrium) construction permit Issued · 21.6 mo
- Abilene Christian University Molten Salt Research Reactor construction permit Issued · 21.9 mo
See all 75 reviews in the NRC Licensing Review Tracker →
Sources
- https://www.nrc.gov/licensing-applications/non-power-facilities/new-facility-licensing/hermes-kairos-application
- https://www.federalregister.gov/d/2021-23568
- https://www.federalregister.gov/d/2021-26119
- https://www.federalregister.gov/d/2023-19006
- https://www.federalregister.gov/d/2023-27960
- https://www.nrc.gov/docs/ML2333/ML23338A258.pdf
- https://www.nrc.gov/regulations-legislation/effectiveness-efficiency-and-timeliness-initiatives-that-support-unleashing-american-energy/licensing-efficiencies