Palisades Nuclear Plant return to power operations (licensing basis restoration)

Issued · Restart · Operating fleet

Palisades Nuclear Plant return to power operations (licensing basis restoration): NRC restart review for Holtec Decommissioning International, LLC / Holtec Palisades, LLC; operating authority transferred to Palisades Energy, LLC — issued, 13.2 months from docketing to decision. Sourced dates and schedule.

Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands

Current state

TypeRestart
OutcomeIssued
ApplicantHoltec Decommissioning International, LLC / Holtec Palisades, LLC; operating authority transferred to Palisades Energy, LLC
FacilityPalisades Nuclear Plant (Covert, Michigan)
Docket50-255
Submitted2024-05-24
Docketed (accepted for review)2024-06-18
NRC planned schedule—
NRC target date2025-07-31
Final safety evaluation—
Decision2025-07-24
Review time (docketed → decision)13.2 mo
Submitted → decision14.0 mo
NRC-reported review duration—
NRC-reported resources vs estimate—

Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.

Notes

First-of-a-kind restart from decommissioning. NRC met its revised July 31, 2025 target (decided 2025-07-24). Follow-on LARs (leak-before-break 08/26/2025, steam generator sleeving 10/30/2025, NFPA 805 11/20/2025, relief requests) are excluded from the bundle. Efficiency page: 'Approved a series of licensing and regulatory actions that will pave the way for the restart of the Palisades Nuclear Plant – a first of its kind action'. Submitted: date = last part of the initial restart bundle; first part (50.82 exemption) submitted 2023-09-28. Holtec's 'Regulatory Path to Reauthorize Power Operations' letter was dated 02/01/2023 (not an application). Docketed: date = acceptance of the last part; first acceptance 2023-11-03. Part 50 docket already existed (no new docketing). Final safety evaluation: Separate safety evaluations accompany each licensing action (issued 2025-07-24); no single FSER. Decision: NRC press release No. 25-046 dated July 24, 2025. NRC page lists 'Final Documentation' 07/24/2025 for the exemption, OL/TS LAR, admin TS LAR, E-plan, QA plan and MSLB LAR (license transfer order 07/16/2025). Power operations licensing basis became effective on August 25, 2025 when Palisades Energy rescinded its 50.82(a)(1) certifications.

Timeline

  • 2024-05-24 — Application received: “By letters dated September 28, 2023, December 6, 2023, December 14, 2023, February 9, 2024, May 1, 2024, and May 24, 2024, Holtec Decommissioning International, LLC (the licensee), submitted an exemption, a license transfer request, and four license amendment requests (LARs) to support resumption of power operations” (source)
  • 2024-06-18 — Accepted for review (docketed): “By letters dated November 3, 2023, January 16, 2024, January 23, 2024, March 18, 2024, May 23, 2024, and June 18, 2024, the U.S. Nuclear Regulatory Commission (NRC) staff notified you that your requests had been accepted for review” (source)
  • 2025-07-24 — Issued: “The Nuclear Regulatory Commission has approved a series of licensing and regulatory actions that will pave the way for restart of the Palisades Nuclear Plant.” (source)

The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.

Also tracked

NNN coverage

About Palisades reactor

Related reviews

See all 75 reviews in the NRC Licensing Review Tracker →

Sources

  1. https://www.nrc.gov/facilities-safety/facility-finder/reactors/pali
  2. https://www.nrc.gov/docs/ML2421/ML24219A420.pdf
  3. https://www.nrc.gov/docs/ML2329/ML23291A440.pdf
  4. https://www.nrc.gov/docs/ML2402/ML24022A117.pdf
  5. https://www.nrc.gov/docs/ML2521/ML25213A079.pdf
  6. https://www.nrc.gov/regulations-legislation/effectiveness-efficiency-and-timeliness-initiatives-that-support-unleashing-american-energy/licensing-efficiencies