Palisades Nuclear Plant

Fuel load · United States · Retired-plant restart

Palisades is Holtec's single-unit ~800 MW PWR on Lake Michigan, retired in May 2022 and set to become the first US reactor returned to service after entering decommissioning. Fuel loading began on 30 August 2026 but is paused after a fuel assembly tilted; the NRC is reviewing Holtec's request to retrieve it.

Background: Palisades fuel loading: Holtec restart timeline and what comes next · NRC reactor licensing process, explained

Current state

StatusFuel load
CountryUnited States
LocationCovert Township, Michigan
PlantPalisades
OperatorHoltec International (Palisades Energy LLC)
Reactor typePWR
Net capacity (MWe)805
Restart typeRetired-plant restart
Shut down2022-05-20
Restart target2026
Years offline4.4
RegulatorNRC reauthorised power-operations licensing basis (July 2025); plant returned to operational licensing status Aug 2025; LAR to retrieve tilted fuel assembly filed 2026-09-30, under NRC review
OfftakerWolverine Power Cooperative and Hoosier Energy (long-term PPAs, roughly half the output each)
Public fundingDOE loan up to $1.52bn (closed Sept 2024); USDA New ERA awards of ~$1.3bn to Wolverine and Hoosier for the PPAs; $300m Michigan state funding

Notes

Status "Fuel load" is approximate: loading of the 204-assembly core began 30 Aug 2026 and is paused (Holtec, 21 Sept 2026). restart target '2026' reflects CEO Kris Singh's July 2026 statement (via ANS/FT) and is at risk; earlier targets (Oct 2025, Feb-Mar 2026) slipped. Capacity: WNN 805 MWe; DOE '800-MW'. Holtec plans a subsequent licence renewal to 2051.

Timeline

  • 2022-05-20 — Entergy removed Palisades from service after 50 years; it was defuelled by 10 June. (source)
  • 2024-09 — DOE closed a loan of up to $1.52bn to Holtec Palisades. (source)
  • 2025-08 — Palisades formally returned to operational status a month after NRC approved the licensing package. (source)
  • 2026-08-30 — Palisades entered Mode 6 and began loading fuel into the reactor vessel. (source)
  • 2026-09-11 — Palisades reconnected to its 345-kV switchyard. (source)
  • 2026-09-30 — Holtec asked the NRC for permission to use custom equipment to move a tilted fuel assembly to the spent fuel pool. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Also tracked

NNN coverage

About Holtec International

About Palisades Nuclear Plant

Related units

See all 45 units in the Nuclear Plant Restarts Tracker →

Sources

  1. Fuel loading under way for Palisades restart, Holtec announces — World Nuclear News, checked 2026-10-11
  2. Progress Report on Palisades' March to Startup — Holtec International (primary), checked 2026-10-11
  3. Palisades (EDF project) — U.S. Department of Energy (primary), checked 2026-10-11
  4. Palisades Nuclear Plant Returns To Operational Status And Ready To Receive Fuel — NucNet, checked 2026-10-11
  5. Wolverine, Hoosier Awarded $1.3 Billion to Aid Nuclear Plant Restart — NRECA (electric.coop), checked 2026-10-11
  6. Palisades: Restart projects, Holtec IPO, lawsuit dismissal—but no restart date — American Nuclear Society, checked 2026-10-11
  7. NRC Reviewing Palisades License Amendment Request, Public Comment Opportunity Open — U.S. Nuclear Regulatory Commission (primary), checked 2026-10-11
  8. A Nuclear Shift Buoyed by Billions, and the Waters of the Great Lakes — Circle of Blue, checked 2026-10-11