Wylfa (Magnox)

Active dismantling · United Kingdom · Deferred (SAFSTOR)

Wylfa was the largest and last of Britain's Magnox stations; generation ceased on 30 December 2015, ending Magnox power in the UK. Defueling finished in September 2019 and Nuclear Restoration Services is now preparing the reactors for care and maintenance.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusActive dismantling
CountryUnited Kingdom
LocationCemaes, Anglesey, Wales
SiteWylfa
UnitsReactor 1, Reactor 2
Unit count2
Reactor typesMagnox
Owner / licenseeNuclear Decommissioning Authority (site licensee: Nuclear Restoration Services)
Decommissioning contractorNuclear Restoration Services
StrategyDeferred (SAFSTOR)
Final shutdown2015-12-30
Decommissioning start2019-09
Spent fuelDefueled by September 2019; 87,890 fuel elements sent to Sellafield for reprocessing.

Notes

Capacity not captured from sources reviewed.

Timeline

  • 1971 — Wylfa began operations. (source)
  • 2015-12-30 — Generation ceased, ending Magnox reactor generation in the UK. (source)
  • 2019-09 — Defueling was completed. (source)
  • 2020 — The NDA announced plans for a continuous reactor decommissioning strategy to bring forward final site clearance. (source)
  • 2026-02-26 — ONR introduced a new regulatory approach for the 12 former Magnox sites. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Wylfa — Office for Nuclear Regulation (primary), checked 2026-10-11
  2. ONR introduces new regulatory approach for former Magnox nuclear sites — Office for Nuclear Regulation (primary), checked 2026-10-11
  3. About NRS — NRS Site Stakeholder Groups (primary), checked 2026-10-11