Nuclear Plant Restarts Tracker

Tokai Daini (Tokai Unit 2)

Approved · Japan · Post-Fukushima restart

Tokai 2 is Japan Atomic Power's 1,060 MWe (net) BWR, the closest Japanese reactor to Tokyo. It holds NRA approval (2018) and a licence to run to 60 years, but its safety works, including a 17-metre seawall found defective in 2023, now run to the second half of FY2028, and local evacuation plans are unfinished.

Background: Palisades fuel loading: Holtec restart timeline and what comes next · NRC reactor licensing process, explained

Current state

StatusApproved
CountryJapan
LocationTokai, Ibaraki Prefecture
PlantTokai
Unit2
OperatorJapan Atomic Power Company (JAPC)
Reactor typeBWR
Net capacity (MWe)1,060
Restart typePost-Fukushima restart
Shut down2011-03-11
Years offline15.6
RegulatorNRA conformity approval 2018-09-26; beyond-40-year operation approved 2018-11-07; revised seawall construction plan under NRA review
Local consentNot obtained; wide-area evacuation plans by surrounding municipalities still being drafted (Aug 2026)

Notes

No restart date has been stated; restart cannot precede completion of safety works (2H FY2028). shut down is the quake trip per JAIF 'Outage (2011.03.11~)'. years offline to 2026-10-11.

Timeline

  • 2011-03-11 — Tokai 2 shut down automatically in the Great East Japan Earthquake. (source)
  • 2014-05-20 — JAPC applied for the NRA conformity review. (source)
  • 2018-09-26 — The NRA officially approved Tokai 2. (source)
  • 2018-11-07 — The NRA approved operation beyond 40 years. (source)
  • 2024-08 — JAPC pushed completion of safety work from September 2024 to December 2026. (source)
  • 2026-08-28 — JAPC said safety works would slip to October 2028-March 2029, the fourth postponement. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related units

See all 45 units in the Nuclear Plant Restarts Tracker →

Sources

  1. Current Status of Nuclear Power Plants in Japan as of August 7, 2026 — Japan Atomic Industrial Forum (JAIF) (primary), checked 2026-10-11
  2. Nuclear Power in Japan — World Nuclear Association, checked 2026-10-11
  3. Further Delay in Completion of Safety Measures at Japan's Tokai Daini Nuclear Power Plant — CINIE, checked 2026-10-11
  4. Japco says 'delay of more than two years' to safety measures at Tokai-2 — NucNet, checked 2026-10-11