Nuclear Plant Restarts Tracker

Tomari Unit 1

Under review · Japan · Post-Fukushima restart

Tomari 1 is a 550 MWe (net) Hokkaido Electric PWR offline since 2011. Its NRA conformity review, applied for in July 2013, is still under way after the regulator prioritised and approved sister unit 3 in 2025.

Background: Palisades fuel loading: Holtec restart timeline and what comes next · NRC reactor licensing process, explained

Current state

StatusUnder review
CountryJapan
LocationTomari, Hokkaido
PlantTomari
Unit1
OperatorHokkaido Electric Power
Reactor typePWR
Net capacity (MWe)550
Restart typePost-Fukushima restart
Shut down2011-04-22
Years offline15.5
RegulatorNRA conformity review in progress (applied 2013-07-08)

Notes

No restart target published. years offline to 2026-10-11.

Timeline

  • 2011-04-22 — Tomari 1 entered an outage. (source)
  • 2013-07-08 — Hokkaido Electric applied for the NRA conformity review. (source)
  • 2025-07-30 — The NRA approved Tomari 3 and said it was still reviewing units 1 and 2. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related units

See all 45 units in the Nuclear Plant Restarts Tracker →

Sources

  1. Current Status of Nuclear Power Plants in Japan as of August 7, 2026 — Japan Atomic Industrial Forum (JAIF) (primary), checked 2026-10-11
  2. Nuclear Power in Japan — World Nuclear Association, checked 2026-10-11
  3. Tomari 3 meets safety requirements, regulator concludes — World Nuclear News, checked 2026-10-11