International edition
Nuclear News Network

Reporting the buildout, from mine to megawatt

New Builds & SMRs

Natrium timeline: every milestone from ARDP award to first power

Every dated milestone in TerraPower's Natrium project — from the October 2020 ARDP award to construction at Kemmerer and the 2031 completion target.

Tower cranes over the excavated nuclear-island foundation at the Kemmerer Natrium site, the retiring Naughton coal plant on the horizon — the timeline from coal town to first-of-a-kind fast reactor. Illustration: NNN
Tower cranes over the excavated nuclear-island foundation at the Kemmerer Natrium site, the retiring Naughton coal plant on the horizon — the timeline from coal town to first-of-a-kind fast reactor. Illustration: NNN

The Natrium project has moved from design announcement to nuclear construction in under six years — fast by nuclear standards, slow by the schedule TerraPower first published. This page is the dated record: every milestone, every slip, every pipeline commitment, with sources. It is updated as new milestones land; for how the technology works, see the Natrium explainer.

Key facts

2020–2021: design to site

2022–2023: money, fuel and the slip to 2030

2024–2025: licensing and early works

2026: permit, construction, pipeline

What's ahead

  • Through 2030 — component manufacturing, nuclear-island civil works, and the operating-license process; HALEU deliveries remain the program's watch item.
  • February 2031 — the owner's construction-completion expectation filed with the NRC.
  • By 2033 — PacifiCorp's forecast for two further units.

Current state (August 2026)

Construction is underway at Kemmerer with the energy-storage island ahead of the nuclear island, component production contracted across a Spanish-Korean-French supply chain, and a commercial pipeline — Meta, PacifiCorp, Utah, Kansas, Korea, the UK — that makes Natrium the advanced design with the most credible path from one plant to many. This timeline is append-only: new milestones are added with dates and sources as they land, and the completion expectation stands at February 2031 until a primary source moves it.

Background

Natrium is TerraPower's advanced plant design: a 345 MWe sodium-cooled fast reactor coupled to molten-salt thermal storage that can boost output to 500 MWe for more than five hours. Its March 2026 NRC construction permit was the first for a commercial non-light-water US power reactor in more than 40 years, and construction of the first unit began in April 2026 at Kemmerer, Wyoming, on the site of a retiring coal plant, with completion expected by early 2031. The announced pipeline beyond Kemmerer includes agreements covering up to eight plants for Meta's data centers, further PacifiCorp units, and UK deployment through the Generic Design Assessment. (As of August 2026.) Read the Natrium explainer.

Questions

When did the Natrium project start?
TerraPower and GE Hitachi unveiled the Natrium design in September 2020, and the US Department of Energy selected it as an Advanced Reactor Demonstration Program flagship in October 2020, with $80 million in initial federal funding.
When did Natrium construction start?
Non-nuclear early works began at Kemmerer, Wyoming in June 2024. Nuclear construction officially began April 23, 2026, seven weeks after the NRC issued the construction permit on March 4, 2026.
When will the Natrium reactor be complete?
The owner has told the NRC it expects construction complete by February 2031, roughly five years from construction start.
Why was Natrium delayed from 2028 to 2030?
Fuel. The design needs HALEU (high-assay low-enriched uranium), and after the Russian supply route closed in 2022 TerraPower moved its completion target from 2028 to 2030 while a Western HALEU supply chain was contracted.
How long did the Natrium construction permit take?
TerraPower submitted the application in March 2024; the NRC docketed it on May 14, 2024, completed its technical review in 18 months against a 27-month schedule, and issued the permit on March 4, 2026 — the first for a commercial non-light-water US power reactor in more than 40 years.
Which Natrium plants are planned beyond Kemmerer?
A January 2026 Meta agreement covers up to eight plants for data centers; PacifiCorp has forecast two more units by 2033; Utah and Kansas deployment agreements were announced in 2025; Hyundai E&C holds an EPC framework for up to eight reactors; and the design entered the UK's Generic Design Assessment in 2026.

Sources

  1. TerraPower's Kemmerer 1 Enters Construction: Timeline of the Natrium Project's Road to First Power — POWER Magazine
  2. NRC Issues Construction Permit for TerraPower's Natrium Advanced Reactor — US Department of Energy
  3. TerraPower Commences Construction on America's First Utility-Scale Advanced Nuclear Power Plant — TerraPower
  4. NRC completes safety review for TerraPower's Kemmerer project — American Nuclear Society
  5. TerraPower's Natrium reactor begins UK GDA process — World Nuclear News
  6. TerraPower becomes first advanced reactor company to join INPO — American Nuclear Society

About Nuclear News Network

Nuclear News Network (NNN) is an independent publication covering the global nuclear energy sector — reactor construction, SMRs, fuel supply, policy, operations and fusion. NNN publishes a daily brief, same-day analysis of major developments, and reference guides used across the industry. Articles are produced by the NNN Newsroom, an editorial automation system with human oversight, under the publication's editorial standards. Ruben Seoane is the founder and main editor of NNN.