Reactor TrackerEgypt

El Dabaa-1

VVER-1200 · 1,100 MWe · Under construction · commercial operation est. 2028

Current state

StatusUnder construction
DesignVVER-1200 (PWR)
Net capacity1,100 MWe
CountryEgypt
VendorRosatom
Owner / operatorNuclear Power Plants Authority (Egypt)
Construction start2022-07-20
Original COD target2028
Current COD estimate2028
Schedule slippage0 years

Notes

Africa's largest nuclear project; four VVER-1200 units (4.8 GW). Grid connection 2028 reconfirmed by Rosatom DG Likhachev July 2026; first fuel H1 2027. Unit 2 RPV installed 2026-07-09. Plant-level Sep 2026: KHNP-NPPA turbine-hall progress review Sep 10 (CINIE); Egypt studying expansion from 4 to 6 units (CINIE, unclear — not asserted).

Milestone log

  • 2022-07-20 — First concrete, Unit 1 (source)
  • 2025-11-15 — Reactor pressure vessel for Unit 1 installed (source)
  • 2026-07-09 — Rosatom confirms schedule - first nuclear fuel delivery targeted for first half of 2027, unit grid connection in 2028 (statement at unit 2 RPV ceremony) (source)
  • 2026-09-26 — Electricity minister Esmat meets ASE head Petrov: fuel-receipt prep for 2027, turbine manufacturing, grid-connection prep reviewed; project on schedule (NPPA/SIS via Ahram) (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.

NNN coverage

On the VVER-1200 design

Sources

  1. https://www.world-nuclear-news.org/articles/el-dabaa-project-reports-progress-on-construction
  2. https://www.world-nuclear-news.org/articles/reactor-vessel-installed-in-el-dabaas-second-unit
  3. https://pris.iaea.org/pris/
  4. https://english.ahram.org.eg/NewsContent/1/1235/577572/Egypt/Urban--Transport/Egypt,-Russia-review-El-Dabaa-preparations-for-nuc.aspx