Leningrad II-3

VVER-1200 · 1,110 MWe · Under construction · commercial operation est. 2029

Current state

StatusUnder construction
DesignVVER-1200 (PWR)
Net capacity1,110 MWe
CountryRussia
VendorRosatom
Owner / operatorRosenergoatom
Construction start2024
Original COD target—
Current COD estimate2029
Schedule slippage—

Notes

Cooling-tower colonnade work began Apr 2026 (Rosenergoatom operator-single-source) — noted, not asserted. Core catcher installed Jun 2026 (NucNet). Replacement VVER-1200s for RBMK units 3&4; 2030/2032 commissioning per Titan-2/Rosenergoatom.

Milestone log

  • 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2029 (source)
  • 2026-06-15 — Core catcher installation completed (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.

NNN coverage

On the VVER-1200 design

Sources

  1. https://world-nuclear.org/information-library/current-and-future-generation/plans-for-new-reactors-worldwide
  2. https://pris.iaea.org/pris/
  3. https://www.nucnet.org/news/installation-of-core-catcher-completed-at-russia-s-leningrad-2-3-nuclear-plant-6-1-2026