Reporting the buildout, from mine to megawatt

Reactor TrackerBangladesh

Rooppur-1

VVER-1200 · 1,080 MWe · Commissioning · commercial operation est. 2026

Current state

StatusCommissioning
DesignVVER-1200 (PWR)
Net capacity1,080 MWe
CountryBangladesh
VendorRosatom
Owner / operatorBangladesh Atomic Energy Commission
Construction start2017-11-30
Original COD target2023
Current COD estimate2026
Schedule slippage+3 years

Notes

Bangladesh newcomer program. End-August 2026 grid connection target MISSED: fuel loading (all 163 assemblies) completed May 2026, but two of three PORV safety valves failed automatic-open tests; each repair/retest cycle takes ~1.5 months (New Age, Prothom Alo, TBS, Energy Bangla, Sep 2026). Minister declined a revised date; Q4 2026 grid connection is an inference — commercial operation likely 2027 if commissioning resumes in Q4. Minor fire 2026-09-07 at temporary project office had no nuclear safety significance.

Milestone log

  • 2017-11-30 — First concrete, Unit 1 (source)
  • 2023-10-05 — First fuel delivered to site (source)
  • 2026-04-28 — Stage-B fuel loading began (source)
  • 2026-06-20 — Grid connection expected end of August 2026 at ~300 MW initial output (minister statement) (source)
  • 2026-09-04 — Minister announces grid supply delayed: two of three safety valves (PORVs) failed to open automatically at test temperature; commissioning halted before criticality stage; no new timeframe given (source)
  • 2026-09-10 — Minister update: one of three PORVs functioning; faulty valves repeatedly inspected/reassembled over past 1.5 months with five Russian specialists on site; September grid supply missed; commissioning halted at critical stage (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.

NNN coverage

On the VVER-1200 design

Sources

  1. https://world-nuclear.org/information-library/current-and-future-generation/plans-for-new-reactors-worldwide
  2. https://pris.iaea.org/pris/
  3. https://www.newagebd.net/post/business-front/312342/rooppur-power-supply-delayed-over-safety-valve-defect-minister
  4. https://en.prothomalo.com/bangladesh/3fhten75fw
  5. https://energybangla.com/rooppur-fire-minor-incident-grid-power-timeline-uncertain/
  6. https://world-nuclear-news.org/articles/nuclear-fuel-loading-completed-at-rooppur-1