Current state
| Status | Commissioning |
| Design | VVER-1200 (PWR) |
| Net capacity | 1,080 MWe |
| Country | Bangladesh |
| Vendor | Rosatom |
| Owner / operator | Bangladesh Atomic Energy Commission |
| Construction start | 2017-11-30 |
| Original COD target | 2023 |
| Current COD estimate | 2026 |
| Schedule slippage | +3 years |
Notes
Bangladesh newcomer program. End-August 2026 grid connection target MISSED: fuel loading (all 163 assemblies) completed May 2026, but two of three PORV safety valves failed automatic-open tests; each repair/retest cycle takes ~1.5 months (New Age, Prothom Alo, TBS, Energy Bangla, Sep 2026). Minister declined a revised date; Q4 2026 grid connection is an inference — commercial operation likely 2027 if commissioning resumes in Q4. Minor fire 2026-09-07 at temporary project office had no nuclear safety significance.
Milestone log
- 2017-11-30 — First concrete, Unit 1 (source)
- 2023-10-05 — First fuel delivered to site (source)
- 2026-04-28 — Stage-B fuel loading began (source)
- 2026-06-20 — Grid connection expected end of August 2026 at ~300 MW initial output (minister statement) (source)
- 2026-09-04 — Minister announces grid supply delayed: two of three safety valves (PORVs) failed to open automatically at test temperature; commissioning halted before criticality stage; no new timeframe given (source)
- 2026-09-10 — Minister update: one of three PORVs functioning; faulty valves repeatedly inspected/reassembled over past 1.5 months with five Russian specialists on site; September grid supply missed; commissioning halted at critical stage (source)
The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.
NNN coverage
On the VVER-1200 design
- The 6 nuclear stories that mattered this week 2026-09-19
- Vietnam picks Rosatom for Ninh Thuan 1, Korea closes on Ninh Thuan 2 2026-09-13
- The 8 nuclear stories that mattered this week 2026-09-05
- Rosatom signs EPC contract for Kazakhstan's first nuclear plant 2026-09-04
- The 6 nuclear stories that mattered this week 2026-08-29
- Akkuyu 2 finishes primary-circuit welding in 73 days 2026-08-29
Sources
- https://world-nuclear.org/information-library/current-and-future-generation/plans-for-new-reactors-worldwide
- https://pris.iaea.org/pris/
- https://www.newagebd.net/post/business-front/312342/rooppur-power-supply-delayed-over-safety-valve-defect-minister
- https://en.prothomalo.com/bangladesh/3fhten75fw
- https://energybangla.com/rooppur-fire-minor-incident-grid-power-timeline-uncertain/
- https://world-nuclear-news.org/articles/nuclear-fuel-loading-completed-at-rooppur-1