Current state
| Status | Grid connected |
| Design | CAP1400 (PWR) |
| Net capacity | 1,400 MWe |
| Country | China |
| Vendor | SPIC |
| Owner / operator | SPIC & Huaneng |
| Construction start | 2020-04-21 |
| Original COD target | — |
| Current COD estimate | 2026 |
| Schedule slippage | — |
Notes
Status moved to Grid connected 2026-09-28 on WNA grid date + Wikipedia operational listing — both secondary; commercial-operation date still blank everywhere, so not commercial. Construction start backfilled to 2020-04-21 (WNA reactor page; populated 2020 refined). Owner SNDPC (org:state-nuclear-power-demonstration-plant): Huaneng 25% at end-2023 per its 2024 bond prospectus, balance SPIC-side; WNA's SPIC 55% / Huaneng 45% is the 2009 founding split. Sister Guohe-1 grid Nov 2024.
Milestone log
- 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2026 (source)
- 2025-09-01 — First grid connection (WNA reactor page, flagged approximate/satellite-derived — may be up to 2 months earlier); Wikipedia CAP1400 table lists unit operational 2025 (source)
The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.