Columbia Fuel Fabrication Facility SNM-1107 40-year licence renewal

Issued · Fuel-cycle licence · Fuel cycle & storage

Columbia Fuel Fabrication Facility SNM-1107 40-year licence renewal: NRC fuel-cycle licence review for Westinghouse Electric Company, LLC — issued, 92.4 months from docketing to decision. Sourced dates and schedule.

Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands

Current state

TypeFuel-cycle licence
OutcomeIssued
ApplicantWestinghouse Electric Company, LLC
FacilityColumbia Fuel Fabrication Facility, Hopkins (Richland County), South Carolina
Docket70-1151
Submitted2012-11-30
Docketed (accepted for review)2014-12-30
NRC planned schedule—
NRC target date—
Final safety evaluation—
Decision2022-09-12
Review time (docketed → decision)92.4 mo
Submitted → decision117.4 mo
NRC-reported review duration—
NRC-reported resources vs estimate—

Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.

Notes

Very long review with a mid-stream change of NEPA path: NRC deferred the review in Feb. 2013 pending a revised application; a final EA/FONSI (June 2018) was withdrawn in Oct. 2019 and a new draft EA issued; NRC then decided an EIS was needed (scoping notice July 2020), draft EIS July 30, 2021, final EIS NUREG-2248 July 29, 2022. Revised LRA dated Sept. 20, 2021. Renewal term 40 years (expires Sept. 12, 2062). Measure from 2014-12-30 acceptance (~7.7 years) rather than the 2012 letter. Licence/permit: SNM-1107.

Timeline

  • 2012-11-30 — Application received: “The NRC has received, by letter dated November 30, 2012, and revised/supplemented on July 31, 2014, and December 27, 2014, a request to renew SNM license number SNM-1107” (source)
  • 2014-12-30 — Accepted for review (docketed): “An NRC administrative completeness review, dated December 30, 2014, found the application acceptable for a technical review.” (source)
  • 2022-09-12 — Issued: “License No. SNM-1107 was issued on September 12, 2022, and is effective as of the date of issuance.” (source)

The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.

NNN coverage

About Westinghouse Electric Company

Related reviews

See all 75 reviews in the NRC Licensing Review Tracker →

Sources

  1. https://www.federalregister.gov/documents/2022/09/16/2022-20026/westinghouse-electric-company-llc-columbia-fuel-fabrication-facility
  2. https://www.federalregister.gov/documents/2015/02/27/2015-04136/westinghouse-electric-company-llc
  3. https://www.federalregister.gov/documents/2019/10/28/2019-23419/westinghouse-electric-company-llc-columbia-fuel-fabrication-facility
  4. https://www.federalregister.gov/documents/2020/07/31/2020-16150/westinghouse-electric-company-llc-columbia-fuel-fabrication-facility
  5. https://www.federalregister.gov/documents/2022/08/05/2022-16627/westinghouse-electric-company-llc-columbia-fuel-fabrication-facility