Chinshan Nuclear Power Plant

Fuel removal · Taiwan · Immediate dismantling

Chinshan, Taiwan's first nuclear plant with two 604 MWe Mark-1 BWRs, closed in 2018-2019 and is in a 25-year decommissioning programme. Both reactor cores were fully defuelled by July 2026, and the government deemed a restart unfeasible because key equipment has already been dismantled.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusFuel removal
CountryTaiwan
LocationShimen, New Taipei
SiteChinshan (First NPP)
UnitsUnit 1, Unit 2
Unit count2
Reactor typesBWR
Owner / licenseeTaiwan Power Company (Taipower)
StrategyImmediate dismantling
Final shutdown2019-07
Decommissioning start2019-07
Target completion2044
Spent fuelCores fully defuelled by July 2026; pool to be emptied 2027-31 into dry storage (NAC MPC outdoor store; Holtec indoor store contracted).
Notable issueYears of local opposition delayed the dry-storage facility needed to empty the pools.

Notes

Unit capacity 604 MWe per NEI (likely gross). Plan stages: defuelling to end-2026, dismantling to 2038, testing to 2041, restoration to 2044.

Timeline

  • 2016-01 — Taipower published a four-stage, 25-year decommissioning plan. (source)
  • 2018-12 — Chinshan 1's operating licence expired and decommissioning was confirmed. (source)
  • 2019-07 — Chinshan 2 entered the decommissioning stage. (source)
  • 2025-11 — The economy ministry deemed a Chinshan restart unfeasible due to extensive dismantlement. (source)
  • 2026-07 — Both Chinshan reactor cores were fully defuelled. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Nuclear Power in Taiwan — World Nuclear Association, checked 2026-10-11
  2. Taiwan clears path to restart reactors — Nuclear Engineering International, checked 2026-10-11
  3. Holtec Awarded Contract to Build Sheltered Used Fuel Storage — Holtec International (primary), checked 2026-10-11
  4. Work starts on Taiwanese fuel storage facility — World Nuclear News, checked 2026-10-11