Current state
| Status | Under construction |
| Design | VVER-1200 (PWR) |
| Net capacity | 1,110 MWe |
| Country | Egypt |
| Vendor | Rosatom |
| Owner / operator | NPPA |
| Construction start | 2022-11-19 |
| Original COD target | — |
| Current COD estimate | 2030 |
| Schedule slippage | — |
Notes
Unit-2 RPV installed 2026-07-09 (WNN; corroborated by Rosatom newsletter coverage of the installation ceremony). Plant-level Sep 2026: ministerial fuel-delivery review (fuel 2027), KHNP turbine-hall progress review, 6-unit expansion study — see el-dabaa-1 notes.
Milestone log
- 2022-11-19 — Construction start (first concrete) (source)
- 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2030 (source)
- 2026-07-09 — 330-t reactor pressure vessel installed at unit 2 (7 months after unit 1's vessel) (source)
The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.
NNN coverage
On the VVER-1200 design
- Akkuyu 1 completes primary-circuit hydraulic tests 2026-10-10
- The 6 nuclear stories that mattered this week 2026-09-19
- Vietnam picks Rosatom for Ninh Thuan 1, Korea closes on Ninh Thuan 2 2026-09-13
- The 8 nuclear stories that mattered this week 2026-09-05
- Rosatom signs EPC contract for Kazakhstan's first nuclear plant 2026-09-04
- The 6 nuclear stories that mattered this week 2026-08-29