Current state
| Status | Under construction |
| Design | CAP1000 (PWR) |
| Net capacity | 1,150 MWe |
| Country | China |
| Vendor | SPIC (CAP1000) |
| Owner / operator | SPIC |
| Construction start | 2023 |
| Original COD target | — |
| Current COD estimate | 2027 |
| Schedule slippage | — |
Notes
On schedule for 2027 commercial operation (56-month plan from April 2023 first concrete). Trajectory mirrors Haiyang-3 with ~10 months lag: external containment dome Feb 2026 vs Mar 2025 for unit 3; final CB-20 module Jun 2026 vs Aug 2025. Milestones are SPIC/CNNC announcements corroborated by World Nuclear News and NucNet.
Milestone log
- 2025-06-24 — Reactor internals (260 t) hoisted into reactor building (RPV installed November 2024) (source)
- 2025-09-06 — Inner steel containment vessel top head (658 t, ~40 m diameter) installed; nuclear island shifted from civil works to installation (source)
- 2026-02-09 — External containment steel dome hoisted into position (source)
- 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2027 (source)
- 2026-06-29 — CB-20 containment water tank module (419 t) installed — last large module; Haiyang Phase II entered installation and commissioning phase (source)
The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.
NNN coverage
About Haiyang-4
- Haiyang-3 completes hot functional testing 2026-08-17
On the CAP1000 design
Sources
- https://world-nuclear.org/information-library/current-and-future-generation/plans-for-new-reactors-worldwide
- https://pris.iaea.org/pris/
- https://www.world-nuclear-news.org/articles/final-module-installed-at-haiyang-4
- https://www.nucnet.org/news/china-announces-progress-at-three-nuclear-construction-sites-2-1-2026
- https://www.world-nuclear-news.org/articles/inner-containment-dome-in-place-at-haiyang-4
- https://www.world-nuclear-news.org/articles/reactor-internals-installed-at-haiyang-4