Sanmen-3

CAP1000 · 1,150 MWe · Commissioning · commercial operation est. 2027

Background: The AP1000 reactor, explained

Current state

StatusCommissioning
DesignCAP1000 (PWR)
Net capacity1,150 MWe
CountryChina
VendorSPIC (CAP1000)
Owner / operatorCNNC
Construction start2022-06-28
Original COD target—
Current COD estimate2027
Schedule slippage—

Notes

Cold functional test completed 2026-02-10, confirmed by NucNet, WNN, CNNC and Chinese state media; commissioning-phase milestones (turbine non-nuclear steam test 2026-06-13) per Chinese industry press. CNNP annual report lists unit in commissioning with commercial operation planned 2027, consistent with baseline. Hot functional tests not yet announced as of 2026-09-15.

Milestone log

  • 2022-06-28 — Construction start (first concrete) (source)
  • 2026-02-10 — Cold functional test (primary circuit hydrostatic test) completed; unit transitioned from installation to commissioning phase (source)
  • 2026-06-13 — Non-nuclear turbine steam test (roll-up to rated 1500 rpm) succeeded in a single attempt (source)
  • 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2027 (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.

NNN coverage

On the CAP1000 design

Sources

  1. https://world-nuclear.org/information-library/current-and-future-generation/plans-for-new-reactors-worldwide
  2. https://pris.iaea.org/pris/
  3. https://www.nucnet.org/news/cold-testing-completed-for-china-s-sanmen-3-cap1000-nuclear-plant-2-5-2026
  4. https://www.world-nuclear-news.org/articles/cold-testing-of-third-sanmen-unit-completed
  5. https://en.cnnc.com.cn/2026-02/18/c_1164475.htm