Reactor TrackerChina

Sanmen-4

CAP1000 · 1,150 MWe · Under construction · commercial operation est. 2027

Background: The AP1000 reactor, explained

Current state

StatusUnder construction
DesignCAP1000 (PWR)
Net capacity1,150 MWe
CountryChina
VendorSPIC (CAP1000)
Owner / operatorCNNC
Construction start2023
Original COD target—
Current COD estimate2027
Schedule slippage—

Notes

In installation phase: reactor building dome hoisted 2025-12-31 and final large-module (CB20) lift 2026-04-26 per CNNC/CNNP disclosures. CNNP 2025 annual report (as of 2026-03-31) lists planned commercial operation 2027 — earlier than the WNA/PRIS 2028 estimate; COD set to operator target 2027 pending independent confirmation. Dome and module milestones trace to CNNC corporate sources.

Milestone log

  • 2023 — Construction start (first concrete) (source)
  • 2025-12-31 — Reactor building dome hoisting completed; unit transitioned into installation phase (CNNP 2025 annual report) (source)
  • 2026-04-26 — 460-tonne CB20 module hoisted into place; final large-module lift of Sanmen Phase II (source)
  • 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2028 (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.

NNN coverage

On the CAP1000 design

Sources

  1. https://world-nuclear.org/information-library/current-and-future-generation/plans-for-new-reactors-worldwide
  2. https://pris.iaea.org/pris/
  3. https://vip.stock.finance.sina.com.cn/corp/view/vCB_AllBulletinDetail.php?stockid=601985&id=12278069