International edition
Nuclear News Network

Reporting the buildout, from mine to megawatt

NRC Licensing Review Tracker

American Centrifuge Plant HALEU demonstration cascade (16 centrifuges, 19.75 wt% U-235) (Amendment 13)

Issued · Fuel-cycle amendment · Fuel cycle & storage

American Centrifuge Plant HALEU demonstration cascade (16 centrifuges, 19.75 wt% U-235) (Amendment 13): NRC fuel-cycle amendment review for American Centrifuge Operating, LLC (Centrus Energy Corp.) — issued. Sourced dates and schedule.

Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands

Current state

TypeFuel-cycle amendment
OutcomeIssued
ApplicantAmerican Centrifuge Operating, LLC (Centrus Energy Corp.)
FacilityAmerican Centrifuge Plant, Piketon, Ohio
Docket70-7004
Submitted2020-04-22
Docketed (accepted for review)—
NRC planned schedule—
NRC target date—
Final safety evaluation—
Decision2021-06-11
Review time (docketed → decision)—
Submitted → decision13.6 mo
NRC-reported review duration—
NRC-reported resources vs estimate—

Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.

Notes

Submittal date ambiguous: NRC page says submittals spanned Dec. 2019–June 2020 (first listed ADAMS ML19352G024); the EA calls the LAR "dated April 22, 2020". April 22, 2020 used. Acceptance date not found. UF6 introduction later authorized by ORR letters June 12, 2023 (Cat III) and Sept. 21, 2023 (Cat II). FR EA notice lists docket 70-7003 (the Lead Cascade docket) while SNM-2011 is docket 70-7004. Fully pre-ADVANCE Act. Licence/permit: SNM-2011.

Timeline

  • 2020-04-22 — Application received: “By letters dated April 22, 2020 (ACO 2020a), May 7, 2020 (ACO 2020b), and May 25, 2021 (ACO 2021) the American Centrifuge Operating, LLC (ACO or the licensee) submitted an application to the U.S. Nuclear Regulatory Commission (NRC) to amend Special Nuclear Materials (SNM) License Number SNM-2011” (source)
  • 2021-06-11 — Issued: “The NRC staff reviewed the application and approved the HALEU demonstration program on June 11, 2021” (source)

The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.

Also tracked

NNN coverage

About American Centrifuge Plant (Piketon)

Related reviews

See all 75 reviews in the NRC Licensing Review Tracker →

Sources

  1. https://www.nrc.gov/facilities-safety/fuel-cycle-facilities/new-fuel-cycle-facility-licensing/gas-centrifuge-enrichment-facility-licensing/centrus-energy-corpamerican-centrifuge-operating-llc-formerly-usec-inc-gas-centrifuge-enrichme
  2. https://www.nrc.gov/docs/ML2108/ML21085A705.pdf
  3. https://www.federalregister.gov/documents/2021/06/14/2021-12356/american-centrifuge-operating-llc-american-centrifuge-plant
  4. https://www.federalregister.gov/documents/2024/04/22/2024-08480/american-centrifuge-operating-llc-completion-of-operational-readiness-reviews