Nuclear Decommissioning Tracker

Fort Calhoun Station

Site restoration · United States · Immediate dismantling

Omaha Public Power District closed the single-unit Fort Calhoun PWR in October 2016 for economic reasons and switched from SAFSTOR to prompt DECON in 2019. Release of the bulk of the site (except the dry-cask pad) is expected in 2026, with an LTP revision under NRC review.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusSite restoration
CountryUnited States
LocationFort Calhoun, Nebraska
SiteFort Calhoun Station
UnitsUnit 1
Unit count1
Reactor typesPWR
Net capacity (MWe)482
Owner / licenseeOmaha Public Power District
StrategyImmediate dismantling
Final shutdown2016-10-24
Decommissioning start2019-12
Target completion2026
Cost estimateUSD 382.2m (as of 2025)
Decommissioning trust fundUSD 339.7m (as of 2025-12-31)
Spent fuelAll fuel in dry storage (Transnuclear NUHOMS) since May 2020; expected DOE removal 2058, ISFSI decommissioned 2059.

Notes

Capacity 482 MWe per WNA. NRC estimated closure 2026 refers to release of the bulk of the site; ISFSI decommissioning planned 2059. Cost = remaining DCE in 2025 dollars ($52.9m license termination + $5.9m site restoration + $323.4m spent fuel management); the 2018 SAFSTOR-based DCE was $1.21bn.

Timeline

  • 2016-10-24 — OPPD permanently shut down Fort Calhoun. (source)
  • 2019-12 — OPPD switched its decommissioning strategy from SAFSTOR to DECON. (source)
  • 2020-05 — Fuel transfer to the ISFSI was completed. (source)
  • 2024-01-31 — NRC approved the License Termination Plan by license amendment. (source)
  • 2025-12-12 — NRC published an environmental assessment on OPPD's LTP Revision 2. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Fort Calhoun Station — U.S. NRC (primary), checked 2026-10-11
  2. Fort Calhoun LTP Revision 2 environmental assessment (FR 2025-12-12) — Federal Register / NRC (primary), checked 2026-10-11
  3. Fort Calhoun Station, Unit No. 1 2026 Annual Decommissioning Funding Status Report — OPPD / U.S. NRC (primary), checked 2026-10-11
  4. Decommissioning Nuclear Facilities — World Nuclear Association, checked 2026-10-11
  5. Locations of Power Reactor Sites Undergoing Decommissioning — U.S. NRC (primary), checked 2026-10-11