Fukushima Daiichi Nuclear Power Station (Units 1-6)

Fuel removal · Japan · Immediate dismantling

TEPCO is decommissioning all six Fukushima Daiichi units under the government's Mid-and-Long-Term Roadmap, targeting completion 30-40 years after the 2011 triple meltdown. Spent fuel removal from Unit 2's pool began on 2 June 2026 and trial fuel-debris retrieval began in 2024, but full-scale debris removal has slipped to 2037 at the earliest.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusFuel removal
CountryJapan
LocationOkuma and Futaba, Fukushima Prefecture
SiteFukushima Daiichi
UnitsUnit 1, Unit 2, Unit 3, Unit 4, Unit 5, Unit 6
Unit count6
Reactor typesBWR
Owner / licenseeTokyo Electric Power Company Holdings (TEPCO)
StrategyImmediate dismantling
Final shutdown2014-01-31
Decommissioning start2011-12
Target completion2051
Spent fuelUnit 4 pool emptied December 2014 and Unit 3 February 2021; Unit 2 pool removal began 2 June 2026; Unit 1 removal due to start FY2027-28; roadmap target is all units' pools emptied within 2031.
Notable issueMelted fuel debris retrieval: only gram-scale samples removed (Nov 2024, Apr 2025); full-scale retrieval delayed to 2037 or later.

Notes

target completion 2051 = roadmap's 30-40 years from December 2011 (TEPCO says 30-40 years; 2051 is the commonly cited end-point, not stated verbatim on pages opened). The government's total Fukushima accident cost estimate is JPY 23.5 trillion (decommissioning + compensation + decontamination, per FoE Japan, March 2026); the decommissioning-only share is not separated here, so cost estimate not recorded.

Timeline

  • 2011-03-11 — An earthquake and tsunami caused meltdowns in Units 1-3 and hydrogen explosions. (source)
  • 2011-12 — The government adopted the original Mid-and-Long-Term Roadmap for decommissioning. (source)
  • 2012-04-19 — Units 1-4 were permanently shut down. (source)
  • 2014-01-31 — Units 5 and 6 were permanently shut down. (source)
  • 2021-02 — All fuel was removed from the Unit 3 spent fuel pool. (source)
  • 2024-09-10 — TEPCO began trial fuel debris retrieval at Unit 2. (source)
  • 2025-07-29 — TEPCO said full-scale debris removal would start in 2037 at the earliest instead of the early 2030s. (source)
  • 2026-06-02 — TEPCO began removing spent fuel from the Unit 2 pool. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Roadmap on the Way to Decommissioning — TEPCO (primary), checked 2026-10-11
  2. Status of Each Unit of the Fukushima Daiichi Nuclear Power Station — TEPCO (primary), checked 2026-10-11
  3. Fuel Removal from Unit 2 Spent Fuel Pool — TEPCO (primary), checked 2026-10-11
  4. Fuel debris removal from Fukushima reactors delayed — World Nuclear News, checked 2026-10-11
  5. Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO's Fukushima Daiichi NPS Units 1-4 — METI (primary), checked 2026-10-11
  6. [Statement] 15 Years Since the Fukushima Daiichi Nuclear Disaster — FoE Japan, checked 2026-10-11
  7. Nuclear Power in Japan — World Nuclear Association, checked 2026-10-11