Active dismantling · Germany · Immediate dismantling

Grohnde, a PWR on the Weser shut on 31 December 2021, has been in dismantling since January 2024. It became fuel-free in April 2026 and received its second and final dismantling permit in May 2026; PreussenElektra targets completion by 2039.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusActive dismantling
CountryGermany
LocationEmmerthal, Lower Saxony
SiteGrohnde
UnitsKWG
Unit count1
Reactor typesPWR
Net capacity (MWe)1,360
Owner / licenseePreussenElektra (E.ON)
StrategyImmediate dismantling
Final shutdown2021-12-31
Decommissioning start2024-01
Target completion2039
Spent fuelAll fuel in CASTOR casks at the on-site Grohnde interim store since 7 April 2026.
Notable issueReactor vessel internals cutting is scheduled to start in early 2027.

Timeline

  • 2021-12-31 — Grohnde ended power operation. (source)
  • 2023-12 — The decommissioning and first dismantling permit was granted. (source)
  • 2024-01 — Dismantling work began. (source)
  • 2026-04-07 — The last CASTOR cask moved to the on-site interim store, making the plant fuel-free. (source)
  • 2026-05-15 — PreussenElektra received the second and final dismantling permit, covering the reactor vessel and biological shield. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Kernkraftwerk Grohnde erhält zweite und letzte Rückbaugenehmigung — PreussenElektra (primary), checked 2026-10-11
  2. Permit issued for second phase of Grohnde dismantling work — World Nuclear News, checked 2026-10-11
  3. Nuclear Power in Germany — World Nuclear Association, checked 2026-10-11