Nuclear Decommissioning Tracker

Hamaoka Units 1 and 2

Active dismantling · Japan · Immediate dismantling

Chubu Electric's Hamaoka 1 and 2 BWRs, closed in 2009 over seismic upgrade costs, are the first Japanese commercial reactors to reach the reactor-dismantling stage. Unit 2's reactor dismantling began in March 2025 and Unit 1's in October 2025; Chubu expects to finish in fiscal 2042.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusActive dismantling
CountryJapan
LocationOmaezaki, Shizuoka Prefecture
SiteHamaoka
UnitsUnit 1, Unit 2
Unit count2
Reactor typesBWR
Owner / licenseeChubu Electric Power
StrategyImmediate dismantling
Final shutdown2009-01
Decommissioning start2009-11
Target completion2042
Notable issueFirst commercial reactors in Japan to enter the reactor-dismantling stage.

Notes

Gross capacities 540 + 840 MWe per WNN (net not given).

Timeline

  • 2009-01 — Chubu decided to close both units rather than upgrade to new seismic standards. (source)
  • 2009-11 — METI approved the four-stage plan and Stage 1 began. (source)
  • 2024-12-18 — The NRA approved moving to Stage 3 (reactor dismantling). (source)
  • 2025-03-17 — Chubu removed Unit 2's pressure vessel upper lid, starting reactor dismantling. (source)
  • 2025-10-10 — Chubu reported removing Unit 1's pressure vessel lid as reactor dismantling began. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Dismantling of Hamaoka 1 reactor under way — World Nuclear News, checked 2026-10-11
  2. Hamaoka Nuclear Power Station Units 1 and 2 Entering ... — Chubu Electric Power (primary), checked 2026-10-11