Nuclear Decommissioning Tracker

Isar Nuclear Power Plant (Isar 1 and 2)

Active dismantling · Germany · Immediate dismantling

PreussenElektra is dismantling both Isar units near Landshut: Isar 1 (BWR, shut 2011) since its 2017 permit, and Isar 2 (Germany's most powerful PWR, shut 15 April 2023) since a March 2024 permit. The operator aims to finish the Essenbach site by the end of the 2030s.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusActive dismantling
CountryGermany
LocationEssenbach, Bavaria
SiteIsar / Ohu
UnitsIsar 1, Isar 2
Unit count2
Reactor typesBWR, PWR
Net capacity (MWe)2,288
Owner / licenseePreussenElektra (E.ON)
StrategyImmediate dismantling
Final shutdown2023-04-15
Decommissioning start2017-01
Spent fuelSpent fuel in CASTOR casks at the on-site interim store (state-run BGZ).
Notable issueIsar 2 was one of the last three German reactors; Bavaria's government opposed the 2023 shutdown. A November 2025 mishap briefly interrupted Isar 2 dismantling.

Notes

Net capacities 878 + 1410 MWe per WNA. Isar 1 legal shutdown date 2011-08-06 per WNA (operation ended March 2011). PreussenElektra target: site dismantled by end of the 2030s (no exact year).

Timeline

  • 2011-03 — Isar 1 was shut down with seven other German reactors after Fukushima. (source)
  • 2017-01 — The decommissioning and dismantling permit for Isar 1 was granted. (source)
  • 2023-04-15 — Isar 2 permanently shut down in Germany's nuclear phase-out. (source)
  • 2024-03 — Bavaria issued the dismantling permit for Isar 2; Isar 1 dismantling was about half complete. (source)
  • 2025-11 — A mishap interrupted Isar 2 dismantling; regular work resumed in March 2026. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Kernkraftwerk Isar — PreussenElektra (primary), checked 2026-10-11
  2. Permit issued for dismantling of Isar 2 — World Nuclear News, checked 2026-10-11
  3. Isar 2 (Niederbayern): Rückbau läuft — Die Bayern, checked 2026-10-11
  4. Zwei Jahre nach dem Atomausstieg läuft bei allen AKW der Rückbau — BASE (Federal Office for the Safety of Nuclear Waste Management) (primary), checked 2026-10-11
  5. Nuclear Power in Germany — World Nuclear Association, checked 2026-10-11