Nuclear Decommissioning Tracker

Ohi (Oi) Units 1 and 2

Active dismantling · Japan · Immediate dismantling

Ohi 1 and 2, two 1,175 MWe ice-condenser PWRs, became in 2017-18 the first post-Fukushima retirements of Japanese reactors over 1,000 MWe. Kansai has been dismantling secondary-system equipment since April 2020 under a plan approved in December 2019.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusActive dismantling
CountryJapan
LocationOhi, Fukui Prefecture
SiteOhi
UnitsUnit 1, Unit 2
Unit count2
Reactor typesPWR
Owner / licenseeKansai Electric Power
StrategyImmediate dismantling
Final shutdown2018-03-01
Decommissioning start2020-04-01
Notable issueOnly Japanese reactors with ice-condenser containment; upgrading the containment walls was deemed uneconomic.

Notes

NucNet: Kansai expects to spend about $1.1bn to dismantle both units (currency-converted figure, so cost estimate not recorded). final shutdown uses the date of the decommissioning application (formal retirement).

Timeline

  • 2017-12-22 — Kansai decided not to seek restart of Ohi 1 and 2. (source)
  • 2018-03-01 — Kansai applied for approval to decommission the units. (source)
  • 2019-12 — The NRA approved the Ohi 1 and 2 decommissioning plan. (source)
  • 2020-04-01 — Dismantling of secondary-system equipment began at both units. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Kansai applies to decommission Ohi 1 and 2 — World Nuclear News, checked 2026-10-11
  2. Regulator Approves Plan To Decommission Ohi-1 And -2 — NucNet, checked 2026-10-11
  3. Kansai Electric Power Nuclear Plant Operations Update (as of June 30, 2026) — Kansai Electric Power IR (via BigGo Finance), checked 2026-10-11