Nuclear Decommissioning Tracker

Onagawa Unit 1

Active dismantling · Japan · Immediate dismantling

Low-confidence record: sources are thin or conflict. Figures below are the best available public statements, not confirmed facts.

Tohoku Electric decided in October 2018 to scrap Onagawa 1, a 524 MWe BWR from 1984 whose cramped containment made post-Fukushima safety upgrades impractical. Its decommissioning plan, filed with the NRA in August 2019, budgets JPY 41.9 billion, of which JPY 30 billion is for dismantling.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusActive dismantling
CountryJapan
LocationOnagawa, Miyagi Prefecture
SiteOnagawa
UnitsUnit 1
Unit count1
Reactor typesBWR
Owner / licenseeTohoku Electric Power
StrategyImmediate dismantling
Final shutdown2018
Cost estimateJPY 41.9bn (as of 2019-08)
Notable issueClosest plant to the 2011 quake epicentre; survived with a turbine-building fire.

Notes

final shutdown = year of retirement decision. Plan approval and current stage of work not confirmed in the sources reviewed.

Timeline

  • 1984 — Onagawa 1 began operating. (source)
  • 2018-10 — Tohoku announced Onagawa 1 would be decommissioned. (source)
  • 2019-08-02 — Tohoku applied to the NRA for approval of its decommissioning plan. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Tohoku submits decommissioning plan for Onagawa 1 — World Nuclear News, checked 2026-10-11
  2. Nuclear Power in Japan — World Nuclear Association, checked 2026-10-11