Nuclear Decommissioning Tracker

Tsuruga Unit 1

Active dismantling · Japan · Immediate dismantling

Tsuruga 1, a 341 MWe BWR that began commercial operation in 1970 as one of Japan's first, ended operation on 27 April 2015 and has been in decommissioning since May 2017. Its sister Unit 2 was refused a restart by the regulator in 2024 over an active fault.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusActive dismantling
CountryJapan
LocationTsuruga, Fukui Prefecture
SiteTsuruga
UnitsUnit 1
Unit count1
Reactor typesBWR
Net capacity (MWe)341
Owner / licenseeJapan Atomic Power Company (JAPC)
StrategyImmediate dismantling
Final shutdown2015-04-27
Decommissioning start2017-05-15

Notes

Capacity 341 MWe per WNA. Commercial-operation date (14 Mar 1970) read from JAPC timeline layout — medium confidence.

Timeline

  • 1970-03-14 — Tsuruga 1 began commercial operation. (source)
  • 2015-04-27 — Operation of Tsuruga 1 was terminated. (source)
  • 2017-05-15 — Decommissioning of Tsuruga 1 started. (source)
  • 2024-07-26 — A Japanese regulator panel decided against restarting neighbouring Tsuruga 2. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. An Overview | The Japan Atomic Power Company — Japan Atomic Power Company (primary), checked 2026-10-11
  2. Nuclear Power in Japan — World Nuclear Association, checked 2026-10-11
  3. Japan nuclear watchdog panel decides against restarting Tsuruga reactor — Reuters, checked 2026-10-11