Current state
| Status | Under construction |
| Design | CAP1000 (PWR) |
| Net capacity | 1,161 MWe |
| Country | China |
| Vendor | SPIC (CAP1000) |
| Owner / operator | SPIC |
| Construction start | 2024 |
| Original COD target | — |
| Current COD estimate | 2031 |
| Schedule slippage | — |
Notes
CA01 module (1,167 t) set 2026-08-29 per CINIE — single source, not asserted. construction start definitional note: excavation Dec 2024, FCD Dec 2025 per WNA/SNERDI (PRIS uses FCD); populated 2024 value frozen pending PRIS-direct review. Net capacity 1161 MWe per the WNA reactor database (1161 net / 1250 gross, data credited to IAEA PRIS), the one source listing both Bailong units, so both carry the same figure (set 2026-10-13); IAEA PRIS's own page showed 1160 net / 1254 gross (3400 MWt; PRIS id 2169) on 2026-10-12. The 1.25 GW per-unit figure in press reports is gross. The 1.25 GW per-unit figure in press reports is gross. PRIS (checked 2026-10-12) also gives construction start 2025-12-22 and construction licence 2024-09-27.
Milestone log
- 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2031 (source)
- 2026-03-24 — CA20 structural module installed in the nuclear island (largest/heaviest NI structural module campaign) (source)
- 2026-08-16 — First inner steel containment ring (CV1R) lifted into design position (4-hour operation, per SPIC) (source)
The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.
NNN coverage
At Bailong Nuclear Power Plant
On the CAP1000 design
Sources
- https://world-nuclear.org/nuclear-reactor-database/summary/report?report=gen&status=Under%20Construction
- https://pris.iaea.org/pris/
- https://pris-stats.iaea.org/reactor/reactors-by-code/CN
- https://world-nuclear.org/nuclear-reactor-database/details/Bailong-1
- https://www.nucnet.org/news/china-installs-first-ring-of-steel-containment-at-bailong-1-nuclear-plant-8-1-2026
- https://www.neimagazine.com/news/key-module-installed-at-bailong-1/