Current state

TypeSubsequent licence renewal
OutcomeIssued
ApplicantConstellation Energy Generation, LLC
FacilityDresden Nuclear Power Station (Dresden 2, Dresden 3)
Docket50-237, 50-249
Submitted2024-04-17
Docketed (accepted for review)2024-06-14
NRC planned schedule—
NRC target date2025-11-13
Final safety evaluation2025-09-09
Decision2025-12-16
Review time (docketed → decision)18.1 mo
Submitted → decision20.0 mo
NRC-reported review duration—
NRC-reported resources vs estimate—

Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.

Notes

Aug 7, 2025 letter also cut the hour estimate to ~12,200 h (from 8,000 safety + 6,000 environmental). The letter does not cite EO 14300. Issued ~1 month after the accelerated target; fetched sources give no reason. No FR notice establishing a Licensing Board was found for this application in an FR API search. NRC decision target: originally 2025-12, latest 2025-11-13. Schedule: Original schedule (NRC letter Aug 2, 2024, ML24184A171) targeted 12/2025; Aug 7, 2025 letter accelerated it to 11/13/2025, citing 'several staff efficiencies'; actual 12/16/2025.

Timeline

  • 2024-04-17 — Application submitted. (source)
  • 2024-06-14 — NRC letter: acceptable for docketing. (source)
  • 2024-06-24 — FR notice of acceptance and opportunity for hearing. (source)
  • 2024-08-02 — NRC issues projected review schedule. (source)
  • 2025-08-07 — Revised schedule letter (decision 11/13/2025). (source)
  • 2025-09-03 — Final SEIS issued. (source)
  • 2025-09-09 — Final safety evaluation issued. (source)
  • 2025-09-09 — Final safety evaluation issued. (source)
  • 2025-12-16 — Subsequent renewed licenses DPR-19 and DPR-25 issued. (source)
  • 2025-12-16 — Issued. (source)

The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.

Also tracked

NNN coverage

About Constellation Energy

Related reviews

See all 75 reviews in the NRC Licensing Review Tracker →

Sources

  1. https://www.nrc.gov/licensing-applications/power-reactor-licensing/dresden-nuclear-power-station-units-2-and-3-subsequent-license-renewal-application
  2. https://www.nrc.gov/docs/ML2519/ML25198A191.pdf
  3. https://www.federalregister.gov/documents/2024/05/07/2024-09951
  4. https://www.federalregister.gov/documents/2024/06/24/2024-13768
  5. https://www.federalregister.gov/documents/2025/12/18/2025-23283
  6. https://www.nrc.gov/sites/default/files/cdn/doc-collection-news/2025/25-066.pdf
  7. https://web.archive.org/web/20240907/https://www.nrc.gov/reactors/operating/licensing/renewal/applications/dresden-subsequent.html
  8. https://www.nrc.gov/licensing-applications/operating-reactor-licensing/reactor-license-renewal/status-subsequent-license-renewal-applications