Current state
| Type | Subsequent licence renewal |
| Outcome | Issued |
| Applicant | Constellation Energy Generation, LLC |
| Facility | Dresden Nuclear Power Station (Dresden 2, Dresden 3) |
| Docket | 50-237, 50-249 |
| Submitted | 2024-04-17 |
| Docketed (accepted for review) | 2024-06-14 |
| NRC planned schedule | — |
| NRC target date | 2025-11-13 |
| Final safety evaluation | 2025-09-09 |
| Decision | 2025-12-16 |
| Review time (docketed → decision) | 18.1 mo |
| Submitted → decision | 20.0 mo |
| NRC-reported review duration | — |
| NRC-reported resources vs estimate | — |
Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.
Notes
Aug 7, 2025 letter also cut the hour estimate to ~12,200 h (from 8,000 safety + 6,000 environmental). The letter does not cite EO 14300. Issued ~1 month after the accelerated target; fetched sources give no reason. No FR notice establishing a Licensing Board was found for this application in an FR API search. NRC decision target: originally 2025-12, latest 2025-11-13. Schedule: Original schedule (NRC letter Aug 2, 2024, ML24184A171) targeted 12/2025; Aug 7, 2025 letter accelerated it to 11/13/2025, citing 'several staff efficiencies'; actual 12/16/2025.
Timeline
- 2024-04-17 — Application submitted. (source)
- 2024-06-14 — NRC letter: acceptable for docketing. (source)
- 2024-06-24 — FR notice of acceptance and opportunity for hearing. (source)
- 2024-08-02 — NRC issues projected review schedule. (source)
- 2025-08-07 — Revised schedule letter (decision 11/13/2025). (source)
- 2025-09-03 — Final SEIS issued. (source)
- 2025-09-09 — Final safety evaluation issued. (source)
- 2025-09-09 — Final safety evaluation issued. (source)
- 2025-12-16 — Subsequent renewed licenses DPR-19 and DPR-25 issued. (source)
- 2025-12-16 — Issued. (source)
The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.
Also tracked
NNN coverage
About Constellation Energy
- The 6 nuclear stories that mattered this week 2026-10-10
- Google, Constellation plan 890 MW in nuclear uprates 2026-10-07
- Nuclear power for data centers, explained: every deal tracked 2026-10-01
- DOE nuclear funding, explained: every program paying for the buildout 2026-08-05
- NNN Daily Brief — July 22, 2026 2026-07-22
- The nuclear decommissioning market in 2026: size, players, pipeline 2026-07-14
Related reviews
- R.E. Ginna Nuclear Power Plant – Subsequent License Renewal Under review · —
- Nine Mile Point Nuclear Station Unit 1 – Subsequent License Renewal Under review · —
- Christopher M. Crane Clean Energy Center (formerly TMI-1) return to power operations Under review · —
- Clinton Power Station Unit 1 – License Renewal Issued · 20.2 mo
- Cooper Nuclear Station – Subsequent License Renewal Under review · —
- Edwin I. Hatch Nuclear Plant Units 1 and 2 – Subsequent License Renewal Issued · 11.9 mo
- H.B. Robinson Steam Electric Plant Unit 2 – Subsequent License Renewal Issued · 11.8 mo
- Browns Ferry Nuclear Plant Units 1, 2 and 3 – Subsequent License Renewal Issued · 20.7 mo
See all 75 reviews in the NRC Licensing Review Tracker →
Sources
- https://www.nrc.gov/licensing-applications/power-reactor-licensing/dresden-nuclear-power-station-units-2-and-3-subsequent-license-renewal-application
- https://www.nrc.gov/docs/ML2519/ML25198A191.pdf
- https://www.federalregister.gov/documents/2024/05/07/2024-09951
- https://www.federalregister.gov/documents/2024/06/24/2024-13768
- https://www.federalregister.gov/documents/2025/12/18/2025-23283
- https://www.nrc.gov/sites/default/files/cdn/doc-collection-news/2025/25-066.pdf
- https://web.archive.org/web/20240907/https://www.nrc.gov/reactors/operating/licensing/renewal/applications/dresden-subsequent.html
- https://www.nrc.gov/licensing-applications/operating-reactor-licensing/reactor-license-renewal/status-subsequent-license-renewal-applications